Preface
In March 2011, the State Council officially approved The Development Plan for Economic Zone on the West Coast of the Taiwan Straits which further defined specific objectives, tasks and pioneering policies for speeding up the construction of the West Coast of the Taiwan Straits. The Development Plan is a new milestone for the development of
We are looking forward to your negotiation and investment for common development.
July 2012
Content
Industry
1. Fuqing Optoelectronic Hi-tech Park (Phase II)
2. Auto Engine Project in Qingkou Investment Zone of
3. Stainless Steel Deep-processing Industrial Park in
4. 300,000 set/a Minicar Construction Project in Longyan
5. Luxury Coach Production Project in Longyan
6. Heavy-duty Truck Production Project in Longyan
7. Auto Engine Production Project in Longyan
8. Engineering Machinery and Auto Tire Production Line in Longyan
9. Production Project of High-pressure Oil Cylinder for Excavators in Xinluo District of Longyan
10. Ladder Truck Production Project in Longyan
11. Bearing Production Project in Longyan
12. Mining Emergency Equipment Production Project in Xinluo District of Longyan
13. Longyan Industrial Park of Material and Equipment Manufacturing for Rial Transit
14. Textile Machinery Manufacturing Project in
15. 20 Million sqm/a Copper Clad Laminate Production Line in
16. High-strength Wear-Resistant Rare Earth Alloy Copper Belt and Bar Production Project in ShanghangCounty
17. Rare Earth Luminescent Material and Application Project in
18. Production Line of Rare Earth Hydrogen Storage Alloy Powder and Nickel-Hydrogen Battery for Electric Automobiles in
19. Sapphire Epitaxial Wafer and Substrate Production Project in
20. Precise Stainless Steel Rolling and Products Project of
21.
22. Industrialization Project of Natural Bamboo Fiber in Nanping
23. Investment Attraction Project of LED Energy-Saving Lighting and Supporting Industrial Chain ofZhangzhou Lantian E& T Development Zone
24. Printing and Packaging Project of High-Tech Zone in
25. Heavy-Duty Equipment Manufacturing Base Project in Ningde
26. Oceaneering Equipment Manufacturing Base in Ningde Haixi Industrial Zone
27. New-Energy Electric Vehicle Project of Fu'an Zhenzhong Electric Manufacture Co., Ltd.
28. Sanming Production Project of Bamboo Fiber
29. Project of Semisolid RP Engine Case of
30. Quangang ABS Resin Project
31. Quangang Polycarbonate (PC) Project
32. Project of LED Chip and Epitaxial Wafer Manufacture and LED Packaging Application of
33. Production Project of High-End Sanitary Wares and Machinery Valve of
34. Production Project of New Ultra-light Board of
35. Manufacturing Project of Large Wind Generating Set of Putian
36. 4,000,000KVA/a Amorphous Metal Transformer Project of
37. Bentonite Development and Deep Processing Project of
38. Manufacturing Project of Hard Alloy Cutting Tool of XinLuo District of
39. 20,000t/a Precision Casting Project of
40. 300,000 sets/a Stainless Steel Centrifugal Pump 1 Project of Wuping County
41. Production Line Project of
42. Dehua Rubber Project
43. Fluorine Chemicals Development Project of
44. Production Project of Special Cable for Vessel of Yanping District in
45. Functional Copolyesters Fiber Project
46. Biomedical Industrial Park of
47. Quangang Phenol-Acetone Project
48. Quangang Acrylonitrile Project
49. Quangang Butyl Rubber Project
50. Quangang Acrylic Fiber Project
51. Hui'an Polyester Project
52. Hui'an
Agriculture
53. Chinese Herbal Crop Planting and Deep Processing Project in Yanping District of
54. Hongxing Green
55. Guanxi Honey Pomelo Industrial Service Platform of
56. Construction Project of Modern Agricultural
57.
58.
59. Finishing Processing Industrialization Project of Tea Seed Soil of Fu'an City
60.
61. Dagang Bay Taiwanese farmers Pioneer Park of Hui'an
62. Jinla Ecological Leisure Fishery Base of Quangang
Services
63. Third Affiliated Hospital of
64.
65. Second-Phase Real Estate Project in
66. Tourism Resource Development Project of
67. Putian Marine Products Refrigeration and Cold Chain Logistics
68. Creative Industries Center of Cross-strait Marine Culture in
69.
70.
71.
72.
73. Development Project of
74.
75. Sandu'ao Coastal Tourism Development Project
76.
77. Construction Project of
78. Taxus Chinensis Cultural
79. Huangchao Ecological Leisure & Tourism Resort in
80. Quanzhou Strait Luggage Logistics Mall
81. National Basketball Training Base in Nan'an City
82.
83. Financial Center Across Taiwan Straits
84.
85. Business Office Project of Xiang'an New Town CBD
86. Haicang Bonded Port
87.
88. Logistics Base of Xiuyu National Processing Demonstration Area for Timber Trade in Putian
89. Large Cold Storage Project of Fruit, Vegetable & Tea Trade Center on West Coast of Taiwan Straits
90. Tourism Development Project of
91. Shaowu Hot Spring Resort
92. Development Project of
93. Construction Project of Five-star Hotel in
94. Zhangzhou Lin Yutang Cultural Park
95. Complex Project of Cultural Tourism in
96. Cross-Straits Aquatic Product Processing Park and Eastern Coast Logistic Center Project
97. Subsidiary Agricultual Product and Featured Product Processing Base in Penghu,
98. Ecotourism Development in
99.
100.
101. Quangang "Archaized Pavilion" Tourism Project at the Bank of the
102.
103. Tourism Area of Family Cai's Ancient Residential Buildings in Nan'an City
Infrastructure
104. Huaxun Asia-Pacific International Incubation Base in
105. Putian Urban Rapid Transit System
106.
107.
108.
109. Construction Project of Northern Section of
110. Construction Project of Yunxiao
111.
112. Storage and Wharf Construction of Operation Zone of
113. Zherong-Chengguan Transit Expressway in
114. Marine Reclamation Construction Project in
115. Highway Project in
116. Xiaocuo Branch Line of Expressway Network on the West Coast of the Taiwan Straits
117. Daitou-Qiulu Section in Putian of Meizhou Bay-Chongqing Expressway
118.
119. Guanling, Fuding-Zherong Section of Multiple Track of Shenhai Expressway
120. Fu'an-Zhangwan Section of Multiple Track of Shenhai Expressway
121. Fuding (Border of
122. Connecting Line between Pingnan and Gutian of West Coast Expressway Network
123. Nanping-Shunchang Expressway
124. Nanping Connecting Line Expressway
125. Zhongxian-Banmian Section in Sanming City of
126. Youxi (Banmian)-Shaxian Section in Sanming City of
127. Daping-Datian Guangping Section in Sanming of
128. Guangping -Shenkou Section in Sanming of
129. Mingxi County Town-Fengxi Section of
130. Sanming Fengxi-Jianning (junction of
131. Zhangzhou Coastal Thoroughfare (Zhao'an Section)
132. Sanming Changshen Expressway Connecting Line
133. Construction Project of Xianyou Laixi-Xiyuan Fengshan Section
134. Reconstruction Project of Suban Township of Xinluo District-Tieshan-Dongxiao-Hongfang-Gaopo Town of Yongding County Section of Provincial Road 203
135. Reconstruction Project of Gutian Gaotouling-Juxia Section of
136. Construction Project of Pingnan Countytown (Jialong Roundabout) -
1. Fuqing Optoelectronic Hi-tech Park (Phase II)
I. Description: introduction of projects like upstream key components, upstream raw materials for intelligent and multifunctional TFT-LCD panels and LCD displays and new LED, OLED backlight into Fuqing Rongqiao Economic and Technological Development Zone.
II. Construction reasons and conditions: as the largest LCD display terminal product production base with the most centralized layout and largest international market share in
III. Total investment: RMB 10 billion or above (depending on specific project). Cooperation mode: exclusive investment or joint venture.
IV. Preliminary work: the Project has been listed in Fuqing Optoelectronics Industry Development Plan with complete infrastructure support facilities.
V. Project organizer: Economic Development Bureau of Administrative Committee of Fuqing Rongqiao Economic and Technological Development Zone
VI. Contact person: Lin Lixiu and Zhang Wen
Tel.: 0591-85377720, 13850148143
0591-85377885, 13950494715
Email:QINGKOU@SINA.COM
2. Auto Engine Project in Qingkou Investment Zone of
I. Description: 500,000 set/a auto engine production line.
II. Construction reasons and conditions: with advantageous location, complete infrastructure support facilities and obvious human cost advantage, Qingkou Investment Zone is an important automobile production base in
III. Total investment: USD 200 million. Cooperation mode: exclusive investment or joint venture.
IV. Preliminary work: infrastructure such as land required for project construction has been provided.
V. Project organizer: Administrative Committee of Qingkou Investment Zone of Fuzhou
VI. Contact person: Chen Qinan
Tel.: 0591-22761310, 13705982615
Fax: 0591-22765053
Email: QINGKOU@SINA.COM
3.
I. Description: with a planned area of 10,018 mu, downstream deep-processing enterprises of stainless steel cold rolling, wire drawing, tubes and pipes, standard parts, non-standard parts, kitchen ware, decoration materials and stainless steel complete sets of equipment are proposed to be introduced to the Park.
II. Construction reasons and conditions: stainless steel industry has been a competitive industry of Luoyuan Bay Economic Development Zone with a complete industrial chain integrating smelting, hot rolling, cold rolling, sheet and wire and other finished products. In addition, convenient transportation of Luoyuan Bay Economic Development Zone can meet the collection, distribution and transportation requirements of stainless steel goods.
III. Total investment: RMB 13 billion. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: after completion, 4 million t/a stainless steel deep-processing capacity can be reached with a newly added annual output of RMB 50 billion.
V. Preliminary work: infrastructure such as water supply, electricity supply and roads has been provided.
VI. Project organizer: Administrative Committee of Luoyuan Bay Economic Development Zone
VII. Contact person: Wang Wenbin
Tel.: 13706972912 Fax: 0591-26982650
4. 300,000 set/a Minicar Construction Project in Longyan
I. Project description: a 300,000 set/a minicar production project divided into two phases - 150,000 set/a in Phase I, including 100,000 set/a FJ6390 minibus and 50,000 set/a FJ1020JA minivan; 300,000 set/a in Phase II.
II. Construction reasons and conditions: as an important part of
III. Total investment: RMB 2.395 billion. Cooperation mode: joint venture with domestic large enterprises.
IV. Analysis of economic benefits: an annual gross profit of RMB 410.22 million and annual net profit of RMB 307.66 million will be achieved under normal operation upon completion of the Project and the payback period is estimated to be 7.25 years.
V. Preliminary work: Phase I is under construction.
VI. Project organizer: Economic and Trade Commission of Longyan City
VII. Contact person: Lai Shuimei
Tel: 0597-3293206,13507538866
5. Luxury Coach Production Project in Longyan
I. Project description: 5,000 set/a luxury coach production line with a planned total investment of RMB 600 million.
II. Construction reasons and conditions: as an important part of
III. Total investment: RMB 1.28 billion. Cooperation mode: joint venture or cooperation with domestic large enterprises.
IV. Preliminary work: the project proposal has been finished.
V. Project organizer: Economic and Trade Commission of Longyan City
VI. Contact person: Lai Shuimei
Tel: 0597-3293206,13507538866
6. Heavy-duty Truck Production Project in Longyan
I. Project description: 30,000 set/a medium- and heavy-duty truck production line.
II. Construction reasons and conditions: as an important part of
III. Total investment: RMB 1 billion. Cooperation mode: cooperation with domestic large enterprises.
IV. Preliminary work: the project proposal has been finished.
V. Project organizer: Economic and Trade Commission of Longyan City
VI. Contact person: Lai Shuimei
Tel: 0597-3293206,13507538866
7. Auto Engine Production Project in Longyan
I. Project description: 5 production lines and research centers for machining of organisms and cylinder head, complete vehicle assembly and test and painting and packaging.
II. Construction reasons and conditions: with the improvement of domestic highway network and rapid economic and social development, the demand for high-powered engine used for medium- and heavy-duty trucks, high-speed luxury coach and high-powered engineering machinery also increases. In particular, the market demand potential for heavy-duty vehicle with an over 360-horsepower and weight over 16 tons is huge.
III. Total investment: RMB 2.5 billion. Cooperation mode: exclusive investment from domestic large enterprises.
IV. Analysis of economic benefits: the annual sales revenue is expected to reach RMB 3.8 billion.
V. Preliminary work: the project proposal has been prepared.
VI. Project organizer:
VII. Contact person: Wu Hongkui
Tel: 13959478254
8. Engineering Machinery and Auto Tire Production Line in Longyan
I. Project description: one production workshop for the new mixing center and a butyl inner-tube production line will be constructed. After completion, the project will produce 30,000 truck tires for industrial vehicles and tires for New Longma medium- and heavy-duty trucks, high-grade SUVs, luxury coaches, agricultural vehicles and dump trucks as well as 1 million natural-rubber inner tubes and butyl inner tubes with different specifications per year.
II. Construction reasons and conditions: the market prospect of tire processing production line for loaders, excavators, New Longma medium- and heavy-duty trucks, high-grade SUVs, luxury coaches, agricultural vehicles and dump trucks is broad. The project site is endowed with improved infrastructure and convenient transportation conditions. Projects such as New Longma medium- and heavy-duty trucks, top-grade SUVs, luxury coaches and dump trucks are introduced to Longyan, laying a solid development foundation for tire production.
III. Total investment: RMB 1.5 billion. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the annual sales revenue will be RMB 3 billion and the profit RMB 300 million when production capacity is reached.
V. Preliminary work: the project proposal has been prepared.
VI. Project organizer: Administrative Committee of Longyan Economic Development Zone
VII. Contact person: Zhang Siyuan
Tel: 0597-3212151, 13859566812
9. Production Project of High-pressure Oil Cylinder for Excavators in Xinluo District of Longyan
I. Project description: 200,000 set/a high-pressure oil cylinder for excavators.
II. Construction reasons and conditions: rapid development of
III. Total investment: RMB 654.80 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: it is expected that the annual output value will reach RMB 1,051.50 million.
V. Preliminary work: the feasibility report has been initially completed.
VI. Project organizer: Investment Promotion Bureau of Xinluo District
VII. Contact person: Qiu Zhidong
Tel: 0597-2338889, 13600987787
10. Ladder Truck Production Project in Longyan
I. Project description: a 500 set/a ladder truck production line constructed by introducing advanced production technology and equipment.
II. Construction reasons and conditions: as the most complete and largest production base for cargo trucks and special-purpose vehicles and an important mechanical equipment industrial base in
III. Total investment: RMB 1.2 billion. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: when production capacity is reached, the annual sales revenue, tax and net profit will reach RMB 2 billion, RMB 180 million and RMB 220 million respectively.
V. Preliminary work: analysis on project investment opportunity, project site selection and comparison and market research of project products have been completed.
VI. Project organizer:
VII. Contact person: Chen Kaiwu
Tel: 0597-3212161, 13859566516
11. Bearing Production Project in Longyan
I. Project description: 200,000 set/a bearing for heavy-duty truck and engineering machinery, 80,000 set/a bearing for high-speed coach and 20,000 set/a bearing for finishing rolling mill and ancillary equipment.
II. Construction reasons and conditions: machinery industry is a pillar industry of Longyan, which is supported by a machinery industry cluster led by engineering machinery and environmental-friendly machinery already shaped. Longyan has a large number of technical personnel and skilled workers with machinery processing and production experience as well as sufficient labor resource. Infrastructure of the project site is improving and a modern three-dimensional transportation network composing of one airport, four railways, 4 expressways and eight national and provincial highways has been established.
III. Total investment: RMB 550 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the annual sales revenue and the profit and tax will be RMB 1 billion and RMB 250 million respectively when production capacity is reached.
V. Preliminary work: the feasibility report has been prepared.
VI. Project organizer:
VII. Contact person: Wu Hongkui
Tel: 13959478254
12. Mining Emergency Equipment Production Project in Xinluo District of Longyan
I. Project description: 2,000 set/a fixed shelter and mobile escape capsule.
II. Construction reasons and conditions: mining emergency shelter is a confined space in dangerous work space under shaft. The fixed shelter generally is dug along the tunnel wall with good air tightness and can withstand impaction exerted by external force. A good internal survival environment can be formed by detecting parameters of the emergency shelter and operate internal survival systems to buy time for survival.
III. Total investment: RMB 812.25 million. Cooperation mode: exclusive investment.
IV. Analysis of economic analysis: when production capacity is reached, the sales revenue can reach RMB 2 billion under normal operation. The return on investment and profit and tax investment ratio will be 28.1% and 35.5% respectively and the payback period is estimated to be 10.56 years.
V. Preliminary work: the feasibility report has been prepared and application for land approval is underway.
VI. Project organizer: Economic and Technological Development Zone in Xinluo District
VII. Contact person: Qiu Zhidong
Tel: 0597-2338889, 13600987787
13. Longyan Industrial Park of Material and Equipment Manufacturing for Rial Transit
I. Project description: it is planned to construct a large industrial park of material and equipment manufacturing for high-speed rail integrating interiors and equipment of rail, cooper-steel composite of steel core and copper sheet, track board of ballastless track system, fasteners of high-speed rail, CA mostar and dedicated asphalt emulsion, PU tie and sound barrier of high-speed rail.
II. Construction reasons and conditions: as an emerging strategic industry, high-speed rail enjoys outstanding advantages of high speed, high capacity, land and energy saving and environmental protection, thus it is of profound significance for accelerating transformation of economic development mode, building modern integrated transportation system, implementing sustainable development strategy and promoting sound and fast economic and social development.
III. Total investment: RMB 5 billion. Cooperation mode: exclusive investment from domestic large enterprise.
IV. Preliminary work: the project proposal has been finished.
V. Project organizer:
VI. Contact person: Wu Hongkui
Tel: 0597-3212126, 13959478254
14. Textile Machinery Manufacturing Project in
I. Project description: 3,000 set/a spinning machine and supporting post-processing equipment
II. Construction reasons and conditions: there are many textile producers in
III. Total investment: RMB 300 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: after completion, the annual output will be RMB 600 million and the annual profit will be RMB 60 million.
V. Preliminary work: project proposal has been completed.
VI. Project organizer: Bureau of Textile Industry of Changting County
VII. Contact person: Lan Youhao
Tel: 13605924179
15. 20 Million sqm/a Copper Clad Laminate Production Line in
I. Project description: 9 productions lines for producing 23.13 million sqm medium and high frequency copper clad laminate
II. Construction reasons and conditions: an industrial chain integrating copper product selecting, smelting, fine processing and deep processing has initially take shape in
III. Total investment: RMB 1 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: after completion, the annual turnover and profit in normal years can reach RMB 4.455 billion and 1.14394 billion respectively with the payback period being 4.5 years.
V. Preliminary work: feasibility study report of the Project has been completed.
VI. Project organizer: Bureau of Copper Industry of Shanghang County
VII. Contact person: Lin Qingguang
Tel: 0597-3995468, 13850635878
16. High-strength Wear-Resistant Rare Earth Alloy Copper Belt and Bar Production Project in Shanghang County
I. Project description: 20,000 t/a rare earth alloy copper belt and rod production line.
II. Construction reasons and conditions: rare earth can purify, metamorphose and alloy copper alloy and can significantly improve the performance of copper alloy. If 0.05% of rare earth is added into pure copper, the conductivity of copper can reach 103%IACS.
III. Total investment: RMB 1.85 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the annual output and profit can reach RMB 600 million and RMB 140 million respectively.
V. Preliminary work: the feasibility report has been completed.
VI. Project organizer: Economic and Trade Bureau of Shanghang County
VII. Contact person: Peng Xurong
Tel: 13605903272
17. Rare Earth Luminescent Material and Application Project in
I. Project description:
II. Construction reasons and conditions: fluorescent lamp is characterized by high light efficiency, good color rendering index, energy conservation and long service life and has broad market prospect. Conditions for mass production of energy-saving lamp are ripe.
III. Total investment: RMB 520 million. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the annual revenue will be RMB 2.5 billion and the annual profit will be RMB 340 million upon completion of the Project.
V. Preliminary work: project demonstration has been finished.
VI. Project organizer: Rare Earth Industry Office of Changting County
VII. Contact person: Zhong Keliang
Tel: 13600996699
18. Production Line of Rare Earth Hydrogen Storage Alloy Powder and Nickel-Hydrogen Battery for Electric Automobiles in
I. Project description: 3,000 t/a high-performance rare earth hydrogen storage alloy powder and 100,000 set/a nickel-hydrogen battery for electric automobiles
II. Construction reasons and conditions:
III. Total investment: RMB 1.02123 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the newly added annual sales income will be RMB 2.5304 billion and the profit will be RMB 250 million upon completion.
V. Preliminary work: the feasibility report and supply of water, electricity and road and leveled ground have been completed.
VI. Project organizer: Rare Earth Industry Office of Changting County
VII. Contact person: Zhong Keliang
Tel: 13600996699
19. Sapphire Epitaxial Wafer and Substrate Production Project in
I. Project description: 200,000 pcs/a 2-inch sapphire substrate, 50,000 piece/a 4-inch sapphire substrate and 150,000 piece/a 4-inch sapphire epitaxial wafer.
II. Construction reasons and conditions: as an important crystalline material, sapphire substrate has been widely used in hi-tech fields such as windows and reflectors of lasers and epitaxial substrate for semiconductor (silicon). Sapphire epitaxial wafer uses sapphire substrate as substrate and after a GaN luminescent thin film or other films grows epitaxially on the sapphire substrate, the Sapphire epitaxial wafer can be used in LED chips.
III. Total investment: RMB 800 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the investment payback period will be 5 years.
V. Preliminary work: land planning of the Project has been completed.
VI. Project organizer: Investment Promotion Bureau of Liancheng County
VII. Contact person: Luo Liqin
Tel: 13959067228
20. Precise Stainless Steel Rolling and Products Project of
I. Project description: it is planned to build a 100,000t/a precise stainless steel rolling and products project. The product includes 100,000t 200~400 series of stainless steel bands which are 0.08~
II. Construction reasons and conditions: stainless steel is characterized by elegant appearance, strong corrosion resistance, high resistance to wear and high intensity and widely applied in many fields of commercial manufacture and daily life. Wuping, located at the boundary of
III. Total investment: RMB 560 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: annual sales revenue is estimated to be RMB 157.5 million and taxes and profits are estimated to be RMB 393.75 million.
V. Preliminary work: project proposal has been prepared.
VI. Project organizer: Investment Promotion Department of
VII. Contact person: Wen Quan
Tel: 15880615720
21.
I. Project description: it is planned to build production lines of thin film solar cell and make R&D for the technologies such as photovoltaic conversion of solar energy.
II. Construction reasons and conditions: Fujian Jimin Electronic Technology Co., Ltd. is located in
III. Total investment: RMB 1 billion. Cooperation mode: cooperation, exclusive investment or joint venture.
IV. Preliminary work: overall planning, feasibility study, project approval and environmental impact assessment have been finished and most plants have been completed.
V. Project organizer: Fujian Jimin Electronic Technology Co., Ltd.
VI. Contact person: Xu Shiting
Tel: 13950690979
22. Industrialization Project of Natural Bamboo Fiber in Nanping
I. Project description: covering an area of 500mu (1mu=
II. Construction reasons and conditions: fine natural bamboo fiber new technology independently developed by Fujian HBS Chemical Technology Co., Ltd. and possessed with industrialization conditions will be adopted for production of natural bamboo fiber. The Company has proprietary intellectual property rights, and its core technology, i.e. "Prepare natural bamboo fiber from organisms by solvent method", has obtained national invention patent (Patent No. ZL2009 1 0111588.7).
III. Total investment: RMB 550 million. Cooperation mode: joint venture, cooperation or equity investment.
IV. Analysis of economic benefits: after the completion of Phase I, the Project will bring RMB 42 million profit and tax; after the completion of Phase II, the Project will bring RMB 1 billion sales revenue and RMB 380 million profit and tax.
V. Preliminary work: at present,
VI. Project organizer: Fujian HBS Chemical Technology Co., Ltd.
VII. Contact person: Jin Biao
Tel.: 0599-6118179, 13850997206
Fax: 0594-6118158 Email: fjhbsgs@163.com
23. Investment Attraction Project of LED Energy-Saving Lighting and Supporting Industrial Chain of Zhangzhou Lantian E& T Development Zone
I. Project description: it is planned to construct an industrial base of LED lighting with a planned area of 600mu.
II. Construction reasons and conditions: an electronic information industrial cluster dominated by LED has been built up in Lantian E& T Development Zone. Currently, there are LED display, LED lighting projects and relevant supporting optoelectronic projects in the Zone. In addition, the Zone possesses key enterprises and post-doctor work stations of high-tech industrial application of energy-saving lighting. Hence, the Zone enjoys sound industrial advantages.
III. Total investment: RMB 3 billion.
IV. Preliminary work: land application and requisition are being carried out.
V. Project organizer: Administrative Committee of Lantian E& T Development Zone
VI. Contact person: Chen Jingyu
Tel: 13906959124
24. Printing and Packaging Project of High-Tech Zone in
I. Project description: it is planned to construct plants and main ancillary buildings such as office building, power distribution room and R&D room with a planned area of 500mu.
II. Construction reasons and conditions: the demand for printing and packaging material in Zhangzhou is about RMB 3 billion every year, which is increasing year by year. But the annual supply is only RMB 600 million, which is far less than the demand. The area where the Project is located has abundant base materials. The Project enjoys the advantages of low cost, high profits, low investment and risk.
III. Total investment: RMB 455 million. Cooperation mode: joint venture or cooperation.
IV. Analysis of economic benefits: it is estimated to bring an annual output value of RMB 680 million and annual profit of RMB 130 million. The payback period will be 4 years. It is indicated that the Project will have prominent economic benefits.
V. Preliminary work: six supplies and one leveling have been completed at the Project site.
VI. Project organizer:
VII. Contact person: Liu Liyou
Tel: 0596-7668888, 13850515110
25. Heavy-Duty Equipment Manufacturing Base Project in Ningde
I. Project description: it is planned to construct a heavy-duty equipment manufacturing base mainly integrating metallurgy equipment, oceaneering equipment, new-energy equipment, equipment of coal chemical industry, harbor machinery and large engineering machinery.
II. Construction reasons and conditions: Ningde has abundant resources and deepwater wharfs along the coast. The construction of the Project can make the best use of advantageous port resource in Ningde, give the strengths of CNOOC and Cosco Shiyard Group into fully play, and finally, promote the economic development of Ningde.
III. Total investment: RMB 2 billion. Cooperation mode: exclusive investment or joint venture.
IV. Preliminary work: overall planning of
V. Project organizer: Ningde Municipal Development and Reform Commission
VI. Contact person: Cheng Weibin
Tel: 0593-2825427, 13509579713
26. Oceaneering Equipment Manufacturing Base in Ningde Haixi Industrial Zone
I. Project description: the Project will cover an area of 3,000mu, mainly manufacturing marine mobile drilling platform (vessels), floating production system, oceaneering workship and auxiliary ship and their key support equipment and systems.
II. Construction reasons and conditions: Ningde has abundant resources and deepwater wharfs along the coast. The construction of the Project can make the best of advantageous port resource in Ningde, give the strengths of CNOOC and Cosco Shiyard Group into fully play, and finally, promote the development of Ningde's economy.
III. Total investment: RMB 3 billion. Cooperation mode: joint venture or exclusive investment.
IV. Preliminary work: the overall plan of Haixi Ningde Industrial Zone, and marine reclamation construction project as launching base of launching project has been completed.
V. Project organizer: Haixi Ningde Industrial Zone Development Co., Ltd.
VI. Contact person: Huang Yicheng
Tel.: 15892124567
27. New-Energy Electric Vehicle Project of Fu'an Zhenzhong Electric Manufacture Co., Ltd.
I. Project description: the project consists of new plants with an area of
II. Construction reasons and conditions: new-energy electric vehicle industry has been listed as one of the seven major emerging strategic industries. Zhenzhong Company is an enterprise specialized in the production of special starter, motor and generator and has developed an annual production capacity of 1 million sets. Thus, it enjoys distinct advantage in producing new-energy electric vehicle.
III. Total investment: RMB 1.5 billion. Cooperation mode: joint venture or cooperation.
IV. Analysis of economic benefits: the estimated payback period of the Project is 8.7 years (including construction period); internal rate of return is 15.70% and the return on investment is 17.53%.
V. Preliminary work: Zhenzhong has developed rare-earth permanent magnet brushless motor dedicated for 0.8KW-30KW electric vehicle, the controller for 0.8KW-30KW electric automobile through cooperation with National University of Defense Technology and two prototypes of 2-4-seat low-speed electric vehicle.
VI. Project organizer: Fu'an Zhenzhong Electric Manufacture Co., Ltd.
VII. Contact person: Lin Zhenzhong
Tel: 13905033562
28. Sanming Production Project of Bamboo Fiber
I. Project description: 100,000t/a bamboo fiber project.
II. Construction reasons and conditions: bamboo fiber is a kind of regenerated cellulose fiber made from natural bamboo through special high-tech process. It is rated as healthy fiber of 21st century and has become a new highlight of domestic and overseas textile market. Sanming enriched with mao bamboo has 380 billion mao bamboos, which provides sufficient raw materials for bamboo fiber production.
III. Total investment: RMB 500 million.
IV. Analysis of economic benefits: after completion and attainment of full capacity, the Project can bring annual sales revenue of RMB 1 billion and profits of RMB 125 million. Total return on investment is 25% and the payback period is estimated to be 4 years.
V. Preliminary work: project planning and design and feasibility study are being carried out.
VI. Project organizer: Sanming Forestry Bureau
VII. Contact person: Chen Aican
Tel: 0598-8288036, 18960591297
29. Project of Semisolid RP Engine Case of
I. Project description: it is planned to build two production lines of aluminum alloy auto engine case with an annual output of 1 million engine cases for different automobiles.
II. Construction reasons and conditions: it is promising to produce high-end and low energy consumption auto engine case with advanced semisolid RP technology. Fujian Rheomet Light Metal Co., Ltd. possesses the exclusive right to use semisolid RM patent of light metal in
III. Total investment: RMB 500 million. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the annual sales revenue will be RMB 1.2 billion, the profit will be RMB 280 million, return on investment will be 40% and the payback period is estimated to be 3.6 years
(including 1 year for construction).
V. Preliminary work: the pre-feasibility report has been compiled.
VI. Project organizer: Development and Reform Bureau of Jiangle County
Tel: 0598-2333091, 13860595382
30. Quangang ABS Resin Project
I. Project description: it is planned to build a 300,000t/a ABS resin production line.
II. Construction reasons and conditions: ABS resin is characterized by high impact resistance, rigidity, oil resistance, low temperature resistance and chemicals resistance, outstanding mechanical strength and electric property, stable processing dimension and good surface glossiness. In addition, ABS resin is easily processed, coated and colored. Furthermore, it can receive secondary processing such as metalizing, electrofacing, pressure welding and adhesive bonding. It is a widely applied thermoplastic engineering plastics. It is estimated that the demand for ABS resin will reach 5.3 million tons in 2015.
III. Total investment: RMB 2,471.2 million. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: annual sales revenue will be RMB 3.45 billion; annual profits and taxes RMB 527.6 million and annual profits RMB 378.3 million with the investment profit-tax rate of 21.4% and the profit rate of 15.3%.
V. Preliminary work: site selection of the Project has been preliminarily completed.
VI. Contact unit: Economic and Trade Bureau of Quangang District
VII. Contact person: Zhuang Tao
Tel: 13860797900 Fax: 0595-87987653
31. Quangang Polycarbonate (PC) Project
I. Project description and site selection: it is planned to build a 100,000t/a PC production line.
II. Construction reasons and conditions: PC is a high-thermoplastic and transparent plastic(with transmittance above 90%)with excellent electric insulativity, extensibility, dimension stability, chemical resistance as well as self-extinguishment, flame resistance and light weight, which is toxic free, healthy, easy to enhance and be colored and available at 135
III. Total investment: RMB 3.05 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the annual average sales revenue is predicted to be RMB 4.4 billion, the annual average total profit and tax amount RMB 720 million, and added value RMB 940 million upon investment.
V. Preliminary work: site selection has been preliminarily completed.
VI. Project organizer: Economic and Trade Bureau of Quangang District
VII. Contact person: Zhuang Tao
Tel.: 13860797900 Fax: 0595-87987653
32. Project of LED Chip and Epitaxial Wafer Manufacture and LED Packaging Application of
I. Project description: 50 set/a LED chip and epitaxial wafer manufacturing equipment and 100KK/a LED packaging application project.
II. Construction reasons and conditions: during "the Twelfth Five-Year Period", opto-electronics industry will have sharp growth. In 2015, it may become the largest industry of 21st century instead of traditional electronics industry. Quanzhou (Hutou)
III. Total investment: RMB 3.3 billion.
IV. Analysis of economic benefits: after completion of the Project, the annual output value will be RMB 2 billion and the profits will be RMB 700 million. The payback period is estimated to be 4 years.
V. Preliminary work: overall land planning has been completed; the land has been leveled and infrastructure building has been started.
VI. Project organizer: Administrative Committee of Quanzhou (Hutou)
VII. Contact person: Lin Zhihuang
Tel: 13505039288 Fax: 0595-23405533
33. Production Project of High-End Sanitary Wares and Machinery Valve of
I. Project description: it is planned to build a production company and the headquarters integrating production, processing, scientific research, exhibition, selling and logistics of hardware, such as sanitary wares and machinery valves, as well as commerce and residence.
II. Construction reasons and conditions: the project site is merely less than
III. Total investment: RMB 1 billion.
IV. Analysis of economic benefits: after completion and attainment of full capacity, the Project will bring an annual output value of over RMB 500 million and create net profits of RMB 80 million. The payback period is estimated to be 6 years.
V. Preliminary work: land planning has been completed and a special service institution has been established.
VI. Project organizer: Fujian Longdu Construction Development Co., Ltd.
VII. Contact person: Wu Yixiong
Tel: 13805931111
34. Production Project of New Ultra-light Board of
I. Project description: an
(1mu≈
II. Construction reasons and conditions: ultra-light board is a kind of board newly developed abroad. It is composed of three layers of materials with glue. Medium density fiberboard, shaving board or plywood can be used as its outer board and as for the core, honeycomb paperboard can be applied. The advantage of ultra-light board is that its weight is only a half of that of the shaving board with the same volume. Hence, the cost of logistics is greatly reduced, making transportation and decoration easier. Moreover, it can obviously cut the consumption of wood materials.
III. Total investment: RMB 230 million. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the annual sales revenue and the profit & tax will be RMB 435 million and RMB 99.2 million respectively, with the profit and tax investment ratio of 38.86%. The investment payback period is estimated to be 4.2 years.
V. Preliminary work: the project proposal is being prepared.
VI. Project organizer:
VII. Contact person: Yang Zhi
Tel.: 0594-5850988 Fax: 0594-5870135
Email: 5857733@163.com
35. Manufacturing Project of Large Wind Generating Set of Putian
I. Project description: it is planned to establish a 100 sets/a wind generating set project with a planning area of 100mu, including
II. Construction reasons and conditions: the development of wind power generation can not only relieve the pressure of energy shortage but also improve the ecological environment and realize sustainable economic development. Import of wind generators from foreign countries may lead to transport troubles and high cost; therefore, it is of great necessity and importance to accelerate the building of domestic wind generator plants for wind power development in
III. Total investment: RMB 202 million. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: the return on investment, the profit and tax investment ratio and FIRR (financial internal rate of return) are estimated to be 15.7%, 27.7% and 15%, respectively.
V. Preliminary work: the project proposal has been finished.
VI. Project organizer:
VII. Contact person: Yang Zhi
Tel.: 0594-5850988 Fax: 0594-5870135 Email: 5857733@163.com
36. 4,000,000KVA/a Amorphous Metal Transformer Project of
I. Project description: in project implementation, five production lines will be built: 1. production line of 20 thousand 30KVA transformers; 2. production line of 20 thousand 50KVA transformers; 3. production line of 10 thousand 63KVA transformers; 4. production line of 10 thousand 80KVA transformers; 5. production line of 10 thousand 100KVA transformers.
II. Construction reasons and conditions: the loss of amorphous metal transformer is nearly 70% lower than that of silicon sheet transformer. Currently, the technologies of amorphous metal transformer have been increasingly mature, which ensures the reliability of products. In addition, amorphous metal transformer can be well operated. Furthermore, it is found in the economic analysis that the loss of amorphous metal transformer can be reduced to a great extent. Hence it can be widely used.
III. Total investment: RMB 400 million. Cooperation mode: cooperation with domestic large enterprises.
IV. Analysis of economic benefits: after completion, the annual sales revenues and net profits will be RMB 1 billion and RMB 118,769.8 thousand with the investment payback period of 3.47 years and the loan repayment period of 1.5 years. Besides, return on investment in the fixed assets and the profit and tax investment ratio are estimated to be 45.03% and 49.6% respectively, which would yield good economic benefits.
V. Preliminary work: the feasibility report has been prepared.
VI. Project organizer: Zhangping Economy and Trade Bureau
VII. Contact person: Yan Yanfen
Tel.: 13600983761
37. Bentonite Development and Deep Processing Project of
I. Project description: the project is of two investment phases. At the first phase, a 100,000t/a active bentonite production line (including 20,000t bentonite granule) will be built; at the second phase, the 5,000t/a organic bentonite production line and 10,000t/a A-type molecular sieve production line will be expanded.
II. Construction reasons and conditions: in accordance with the Detailed Geological Report of Xiewu Section of Wuping Zhongshan Bentonite Mining Area in
III. Total investment: RMB 238 million, including RMB 102 million at the first phase and RMB 136 million at the second phase. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: it is estimated that the annual sales revenue will be RMB 163.2 million and the profits will be RMB 40.8 million after the first-phase work is completed and put into production.
V. Preliminary work: pre-feasibility report has been completed.
VI. Project organizer: Wuping Development and Reform Commission
VII. Contact person: Wu Peiwei
Tel: 13859567678
38. Manufacturing Project of Hard Alloy Cutting Tool of XinLuo District of
I. Project description: it is planned to build a project with an annual output of 450t general and indexable hard alloy blades (including six series: steel (P), cast iron (K), stainless steel (M), nonferrous metal (N), high-temperature alloy (S) and quenched steel (H)), 150t high-performance precision indexable blades; 1 million turning tools, 1 million solid tools and 500 thousand milling cutters.
II. Construction reasons and conditions: in recent years,
III. Total investment: RMB 400 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: it is expected that the annual output value will reach RMB 1 billion
V. Preliminary work: the feasibility report has been initially completed.
VI. Project organizer: Investment Promotion Bureau of Xinluo District
VII. Contact person: Qiu Zhidong
Tel: 0597-2338889, 13600987787
39. 20,000t/a Precision Casting Project of
I. Project description: 20,000t/a precision casting project(including 15,000t cast steel and 5,000t cast iron).
II. Construction reasons and conditions: precision casting is of many advantages such as small covering area, no pollution, high labor productivity, low labor intensity, less investment and short payback period as well as outstanding processing performance. The development of precision casting in Zhangping fills in the gap of precision casting in
III. Total investment: RMB 260 million. Cooperation mode: cooperation with domestic large enterprises.
IV. Analysis of economic benefits: the annual sales revenue will be RMB 500 million and the profits and taxes will be RMB 68 million.
V. Preliminary work: the project proposal has been prepared.
VI. Project organizer: Project Development Office of Zhangping City
VII. Contact person: Li Jianxing
Tel: 0597-7532456, 13850638788
40. 300,000 sets/a Stainless Steel Centrifugal Pump Project of
I. Project description: it is planned to build a 300,000 sets/a stainless steel centrifugal pump production line with a planning area of 160mu. New plants, office buildings, dormitory and other infrastructures will be built with total building area of
II. Construction reasons and conditions: the stainless steel punching centrifugal pump proposed to be produced is suitable for small central air-conditioning. Compared with other casting water pump, it is irreplaceable due to its low noise level and small power. Currently, the annual sales amount of stainless steel punching centrifugal pump has reached hundreds of millions U.S dollars in
III. Total investment: RMB 296.4 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the annual sales revenue and the profits and taxes are estimated to be RMB 750 million and 86.8 million including RMB 20.76 million taxes. Besides, the return on investment and FIRR will be 22.28% and 24.11%, respectively with investment payback period of 4.8 years. Hence, the Project is feasible upon the financial evaluation.
V. Preliminary work: the feasibility report has been compiled.
VI. Project organizer: Management Committee of Wuping Industrial Park
VII. Contact person: Liu Yong
Tel: 0597-3230881, 1385957196
41. Production Line Project of Stainless Steel Road and Bridge Protector of Wuping County
I. Project description: it is proposed to build a project with an annual final assembly of 15,000 sets of stainless steel road and bridge protector, integrating parts manufacturing and technical service. The planning area of the Project is 100mu.
II. Construction reasons and conditions: upon the statistics on national roads, expressways, provincial roads and county/ township/ village roads, 22,000 protectors are needed on national roads and expressways, 40,000 on provincial roads and county/township roads and 250,000 on village roads, totally 312,000 sets. As the service life of the protector is 10 years, its annual demand may be 31,200 sets. Hence, accessories and technical service are of great market potential. In addition, the protectors also have great potential in overseas market. When the growth stage comes, the overseas sales volume will not be lower than 10,000 sets.
III. Total investment: RMB 353.47 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: after completion, the annual output will be RMB 4,650 million, the annual profit RMB 1,801.05 million and the annual revenue tax revenues RMB 302.25 million.
V. Preliminary work: the feasibility report has been compiled.
VI. Project organizer: Wan'an Township People's Government of Wuping County
VII. Contact person: Zhong Yinxiu
Tel: 0597-4802029, 13850637372
42. Dehua Rubber Project
I. Project description: it is proposed to build a production line with an annual output of 50,000t rubber products, including 11,000t natural rubber, 6,000t butadiene styrene rubber and 8,000t 3-polybutadiene rubber.
II. Construction reasons and conditions: the production project of rubber products has a good prospect. Fujian Petrochemical Co., Ltd. and Fujian Petrochemical Industrial Group Co., Ltd. invested a 150,000t rubber project in Quanzhou of Fujian in 2011. It can provide sufficient rubber raw materials for this Project.
III. Total investment: RMB 330 million. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the annual sales revenue will be RMB 1.3 billion; the profits will be RMB 100 million and the payback period will be 4 years upon completion of the Project.
V. Preliminary work: the feasibility study and preliminary design have been completed.
VI. Project organizer: Economic and Trade Bureau of Dehua County
VII. Person in charge: Zheng Xinyan
Tel: 13505090931
Fax: 0595-2358582
43. Fluorine Chemicals Development Project of Jianyang City
I. Project description: it is planned to deeply develop the downstream products of chemical industry, including: 300t/a fluorine- contained pesticide intermediates, such as 2- Chloro- 5- trifluoromethyl pyridinecarboxaldehyde; 1,000t/a finishing agent for fabric; 1,000t/a trifluoroethanol; 20,000t perfluoroethylene and 6,000t/a F12 refrigerant.
II. Construction reasons and conditions: Jianyang and its surrounding area are enriched with fluorite resources. The proved recoverable deposits of fluorite in this area are more than 10 million tons, ranking second in the whole country. Moreover, the fluorite resources here have supreme quality. The annual output of hydrofluoric acid in this area reaches 130,000t. At present, there is still no deep processing company. Jianyang Municipal Party Committee and Government encourage developing fluorine chemicals industry.
III. Total investment: RMB 350 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the investment payback period will be 4 years.
V. Preliminary work: the market research and feasibility study report have been completed.
VI. Project organizer: Investment Promotion Bureau of Jianyang City
VII. Contact person: Zhao Wenhua
Tel: 18960621020
44. Production Project of Special Cable for Vessel of Yanping District in Nanping City
I. Project description: it is planned to build a project with an annual output of
II. Construction reasons and conditions: Nanping, the largest cable production area of
III. Total investment: RMB 300 million. Cooperation mode: exclusive investment.
V. Analysis of economic benefits: after the Project is completed and realizes full capacity, annual sales revenue will be increased by RMB 350 million and the total profits and total profits & taxes will be RMB 34.51 million and RMB 51.03 million, respectively. In addition, the internal rate of ratio (pre-tax) and the break-even point (production capacity utilization) will be 24.54% and 62.18%, respectively. Meanwhile, the investment payback period is estimated to be 5.53 years (including construction period).
V. Preliminary work: the pre-feasibility study report has been prepared by Beijing Machinery Planning Institute.
VI. Project organizer:
VII. Contact person:
Tel:0599-6161825,13905091684 Email:npfgj@163.com
45. Functional Copolyesters Fiber Project
I. Project description: it is planned to build a 200,000t/a project of functional modified copolyesters fiber such as cation fiber, high-shrinkage fiber, anti-static dyeable fiber and profiled hollow fiber.
II. Construction reasons and conditions: high-tech is applied in the Project to study two series of copolyesters and eight categories of fiber; develop easy cationic dyeable short fiber, high-shrinkage filament/ easy disperse dyeable short fiber, DTY, anti-static nano mater batch and anti-static dyeable fiber blended with orga,nic anti-static agent and terpolymer; and produce profiled hollow fiber blended with two kinds of copolyesters. The profiled micropore hollow structure can be realized after alkali treatment. Fiber is easy to dye at normal pressure and has high water absorbability.
III. Total investment: RMB 500 million. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: the annual sales revenue and profits will be RMB 900 million and RMB 80 million respectively upon completion of the Project with an investment payback period of 6.5 years.
V. Preliminary work: the technology of
VI. Project organizer: Economic and Trade Bureau of Yongan City
VII. Contact person: Fan Zuojian
Tel: 0598-3632181, 13605979437
46. Biomedical Industrial Park of Mingxi County
I. Project description: the project is estimated to cover an area of 500mu with total building area of
II. Construction reasons and conditions:
III. Total investment: RMB 560 million. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: the annual trading volume will be RMB 1.3 billion and the annual profits will be RMB 200 million with the investment payback period of 3.5 years after the Project is completed and into operation.
V. Preliminary work: the "Plan of Medicine Town on the West Coast of the Straits" and the pre-feasibility study report have been prepared.
VI. Project organizer: Investment Promotion Bureau of Mingxi County
VII. Contact person: Lin Zengyun
Tel: 13850876357
47. Quangang Phenol-Acetone Project
I. Project description: it is proposed to build a 300,000t/a phenol-acetone production line.
II. Construction reasons and conditions: phenol is an important organic chemical raw material, widely applied and ranking first among the secondary products of benzene in
III. Total investment: RMB 1.02 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the average annual sales revenue, profits & taxes and profit amount are estimated to be RMB 2.24 billion, RMB 210 million and RMB 150 million, respectively. It is predicted that the profit and tax investment ratio and the return on investment will be 20.6% and 14.7% respectively with the investment payback period of 6 years.
V. Contact unit: Construction and Development Company of
VI. Contact person: Chen Gangjun
Tel: 13599776988
48. Quangang Acrylonitrile Project
I. Project description: it is proposed to build a 250,000t/a acrylonitrile production line.
II. Construction reasons and conditions: acrylonitrile is in shortage in
III. Total investment: RMB 1.9 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the average annual sales revenue is predicted to be RMB 3.03 billion, the average annual profits and taxes RMB 560 million and added value RMB 690 million after the Project is put into production.
V. Contact unit: Construction and Development Company of
VI. Contact person: Chen Gangjun
Tel: 13599776988
49. Quangang Butyl Rubber Project
I. Project description and site selection: it is proposed to build a 40,000t/a butyl rubber production line.
II. Construction reasons and conditions: butyl rubber has many advantages including excellent air tightness, good resistance to heat, aging, ozone and solvent, outstanding electric insulation, shock absorption and low water absorbility. What is the most important is that the air tightness of butyl rubber is eight times that of natural rubber, thus being widely applied as inner tube, air cushion and sealing ring. It is the main raw material of auto industry and tire manufacture.
III. Total investment: RMB 1.47 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the average annual sales revenue is estimated to be RMB 800 million, the average annual profits and taxes RMB 250 million and added value RMB 360 million after the Project is put into production.
V. Contact unit: Construction and Development Company of
VI. Contact person: Chen Gangjun
Tel: 13599776988
50. Quangang Acrylic Fiber Project
I. Project description and site selection: it is proposed to build a 150,000t/a acrylic fiber production line.
II. Construction reasons and conditions: acrylic fiber is the trade name of polyacrylonitrile fiber in
III. Total investment: RMB 1.6 billion. Cooperation mode: joint venture or exclusive investment.
IV. Analysis of economic benefits: the average annual sales revenue is estimated to be RMB 2.4 billion, the average annual profits and taxes RMB 400 million and added value RMB 510 million after the Project is put into production
V. Contact unit: Construction and Development Company of
VI. Contact person: Chen Gangjun
Tel: 13599776988
51. Hui'an Polyester Project
I. Project description: it is proposed to build a 600,000t/a polyester production line.
II. Construction reasons and conditions: polyester (PET) belonging to linear unsaturated polyester resin is mainly applied in polyester fiber field and increasingly applied in non-fiber field. PET has outstanding modifiability and recoverability which is favored by people due to increasingly enhanced environmental consciousness. It is predicted that the quantity demand of PET in
III. Total investment: RMB 1.91 billion. Cooperation mode: joint venture or exclusive investment.
IV. Analysis of economic benefits: the average annual sales revenue and total cost are estimated to be RMB 5.88 billion and RMB 5.52 billion. The annual profits will be RMB 240 million with the return on investment of 12.6%. Besides, the investment payback period (pre-tax) will be 9.09 years.
V. Preliminary work: Industrial Layout Planning of Quanhui Petrochemical Industrial Park in Fujian Meizhou Bay Petrochemical Industrial Base has been approved by Fujian Provincial Government and is being implemented. Meanwhile, Regulatory Plan of Quanhui Petrochemical Industrial Park and Key Projects Planning of Quanhui Petrochemical Industrial Park have been finished. The
V. Project organizer: Construction and Development Company of Quanhui Petrochemical Base
VII. Contact person: Chen Shiwei.
Tel: 15059509668 Fax: 0595-87860678
Email: cnqhpc@qq.com
52. Hui'an Steel Module Building Project
I. Project description: the planning area of the Project is 800mu. it is proposed to build steel material processing plant, steel module plant, pipeline and pressure vessel processing plant and outdoor module yard together with one 5,000t dock, two 10,000t wharf and one 30,000t public wharf for bulk cargo.
II. Construction reasons and conditions: steel module building project is quite necessary for the development of maritime engineering, steel bridge engineering and petrochemical engineering. From the perspective of the development trend of maritime engineering, steel module application technology will be widely applied in maritime equipment manufacturing; hence, prefabrication in the onshore base can be realized in the steel structure works and pipeline works such as drilling platform, pipe support platform, one point mooring platform, maritime tower and maritime structures of maritime engineering. This can greatly shorten the marine installation period and reduce the installation difficulty. From the perspective of the development status of steel bridge engineering, steel bridge only occupies only 1% among bridges in
III. Total investment: RMB 800 million. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: the annual output is estimated to be RMB 3 billion and annual profits and taxes RMB 400 million after the completion of the Project.
V. Project organizer: Hui'an
VI. Contact person: Huang Diangui
Tel: 13599178986 Fax: 0595-87391177, 0595-87876568
53. Chinese Herbal Crop Planting and Deep Processing Project in Yanping District of Nanping City
I. Project description: it is planned to build a high-quality Chinese herbal crop production base covering an area of tens of thousands mu and a processing & sales system as well as a technical support system. Importance will be attached to the development of herbal medicine and the building of woody medicine production base. The Project will realize the annual output of
II. Construction reasons and conditions: traditional Chinese medicines become more and more popular for its little toxic and side effects. Mountainous Yanping District and the surrounding area are very suitable for the growth of Chinese herbal crop. Thus, this area is rich in wild Chinese herbal medicines. Moreover, the herbal crops grow in the natural environment free of pollution, thus being of good quality and a plenty of effective medicinal ingredients.
III. Total investment: RMB 50 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the Chinese herbal crop base can realize an annual output of
V. Preliminary work: the project proposal has been finished.
VI. Project organizer:
VII. Contact person:
Tel: 0599-6161825, 13905091684
E-mail: npfgj@163.com
54. Hongxing Green Plum Industrialization Project of Zhao'an County
I. Project description: it is proposed build a 3,000t/a green plum vinegar production line, a 1,500t/a production line of high light transmission green plum juice concentrate and a 12,000t/a green plum juice production line.
II. Construction reasons and conditions: green plum, crowned as a typical kind of food of strong physiological alkalinity, can neutralize acidic foods and make the blood slightly alkalinous. "Zhao'an Hongxing Green Plum" has passed the national registration certification of regional origin mark and green food mark certification successively and won national quality certification trademark. In the whole county, the planting area of green plum reaches 130,000mu with an annual output of 60,000t. It is the largest green plum production and processing base.
III. Total investment: RMB 61.8 million. Cooperation mode: joint venture or exclusive investment.
IV. Analysis of economic benefits: the production project of green plum vinegar will realize an annual output value of RMB 60 million with expected payback period of 3 years. The production project of high light transmission green plum juice concentrate will create an annual output of 132 million with expected payback period of 3 years.
V. Preliminary work: the feasibility study report has been finished.
VI. Project organizer: Fujian Zhao'an Sihai Food Co., Ltd.
VII. Contact person: Huang Yingqiang
Tel: 13306969609
55. Guanxi Honey Pomelo Industrial Service Platform of Pinghe County
I. Project description: it is planned to build a information network service platform of honey pomelo industry, R&D lab of honey pomelo products, logistics center, integrated production workshop and warehouse.
II. Construction reasons and conditions: total planting area of Guanxi honey pomelo in
III. Total investment: RMB 80 million. Cooperation mode: capital increment or joint venture.
IV. Analysis of economic benefits: the annual output value is expected to be RMB 350 million. The annual sales revenue will be increased by RMB 48 million, after-tax operating profits by RMB 23,228.4 thousand and the income tax paid by RMB 5,409.5 thousand. Meanwhile, the Project provides employment opportunities for 1,500 persons.
V. Preliminary work: three supplies (water, electricity and road) and one leveling (ground leveling) have been completed.
VI. Project organizer: Fujian Nanhai Food Co., Ltd.
VII. Contact person: Lin Shunfa
Tel: 13607563563
56. Construction Project of Modern Agricultural Tourism Park
I. Project description: the project covers an area of 350mu. It is proposed to set a 250 mu growing area of honey pomelo and greenhouse special vegetables. In addition, a leisure corridor will be built on both sides of road, covering an area of 50mu. 50 mu residential areas will be built for tour and sightseeing.
II. Construction reasons and conditions: a modern agricultural sightseeing park is built to satisfy human's dream of "back to nature". It is necessary to accelerate building modern agricultural sightseeing park so as to develop the economy of the county. Meanwhile, modern agricultural sightseeing park is necessary for Pinghe to develop its tourism resources.
III. Total investment: RMB 50 million. Cooperation mode: capital increment or joint venture
IV. Analysis of economic benefits: the annual sales revenue is estimated to be increased by RMB 55 million, after-tax operation profits by RMB 13,228.4 thousand and income tax paid by RMB 4,409.5 thousand after completion of the Project.
V. Preliminary work: three supplies (water, electricity and road) and one leveling (ground leveling) have been completed.
VI. Project organizer: Fujian Nanhai Food Co., Ltd.
VII. Contact person: Lin Shunfa
Tel: 13607563563
57. Jinshan Town Deep Pork Processing Project of Nanjing County
I. Project description: it is planned to build a slaughter floor with an annual slaughtering number of more than 200,000 live pigs and deep processing workshop of meat and produce pork leisure food so as to extend the industrial chain of live pig and increase the benefits of live pig cultivation.
II. Construction reasons and conditions: there are 19 village committees in the whole
III. Total investment: RMB 40 million.
IV. Analysis of economic benefits: suppose that the annual output of pollution-free live pigs is 200,000 and the income from each pig will be increased by RMB 100 upon the implementation of the Project. It is calculated that the Project can realize an income increment of RMB 20 million. Hence the investment payback period will be 2 years.
V. Preliminary work: the feasibility proposal has been finished.
VI. Project organizer:
VII. Contact person: Lai Mingkun
Tel: 0596-7551001, 13656073675 Fax: 0596-7551028 E-mail: mklai@126.com
58. Fengtian Town Orchid Expo Park of Nanjing County
I. Project description: it is planned to build a
II. Construction reasons and conditions: in
III. Total investment: RMB 94.6 million. Cooperation mode: cooperation or joint venture.
IV. Analysis of economic benefits: orchid has good economic benefits for its high value added.
V. Preliminary work: a 230mu orchid park has been built and the overall planning is being implemented.
VI. Project organizer: Nanjing County Jingfeng Flower Development Co., Ltd.
VII. Contact person: Zhang Guoming
Tel: 13959676618
59. Finishing Processing Industrialization Project of Tea Seed Soil of Fu'an City
I. Project description: it is proposed to make technical transformation on the 150,000mu tea oil tree base and build a 5,000t/a tea seed oil production line.
II. Construction reasons and conditions: tea seed oil is a kind of high-quality edible oil which is pure, scented and nutritional. It has the functions of reducing blood pressure and blood fat and softening blood vessel. It can not only improve the immune capacity but also be processed into high-class skin care product.
III. Total investment: RMB 150 million. Cooperation mode: joint venture or exclusive investment.
IV. Analysis of economic benefits: the output value is estimated to be RMB 300 million after the Project is completed and put into production.
V. Preliminary work: currently, the tea oil tree forest in the city covers an area of over 300,000mu with an annual output of 1,600t tea oil. Last year, the output value of tea oil trees exceeded RMB 100 million.
VI. Project organizer: Shangbaishi Town Government of Fu'an City
VII. Contact person: Chen Bochong
Tel: 0593-6698001, 13905933597
60. Taiwan Agricultural Technology Exchange and Promotion Center in Quanzhou Taiwanese Investment Zone
I. Project description: the planning area of the Project is 1,000mu. It is proposed to introduce new agricultural technologies from
II. Construction reasons and conditions: as the first national level agricultural cooperation, communication and promotion platform between Taiwan and Fujian, the Center will promote the popularization and application of agricultural technologies and fine varieties of Taiwan in Chinese mainland and boost cross-straits agricultural communication and cooperation in depth and breadth according to the goal of promotion in "new species, new technology, new fertilizer, new pesticide and new machines".
III. Total investment: RMB 50 million. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Preliminary work: infrastructures have been built. As for the first phase engineering, a 500 mu land has been developed.
V. Project organizer: Quanzhou
VI. Contact person: Zhuang Biyu and Zhuang Weidong
Tel.: 13808529689, 18959707273
E-mail:qz27308666@163.com
61. Dagang Bay Taiwanese farmers Pioneer Park of Hui'an
I. Project description: the planning area of
II. Construction reasons and conditions:
III. Total investment: RMB 800 million. Cooperation mode: exclusive investment, joint venture or cooperation. Both overall development and development by zone are accepted.
IV. Analysis of economic benefits: after completion of the Project, diversified three-dimensional ecological breeding mode will be formed in
V. Preliminary work: overall planning of the Project has been finished by Fisheries Research Institute of Fujian. The Park is awarded
VI. Contact person: Zhang Jiannan
Tel: 13960202426 Fax: 0595-87390320
62. Jinla Ecological Leisure Fishery Base of Quangang
I. Project description: it is planned to build some catering and recreation facilities and develop a 1,000mu high-class ecological leisure fishery base based on existing 785mu enclosed standardized prawn pond and coastal roads and wharfs.
II. Construction reasons and conditions: Jinla Aquaculture Company, the largest aquaculture company in Quangang District, owns 17 indoor abalone seedlings growing ponds and 21 indoor adult abalone culture ponds with total building area of
III. Total investment: RMB 30 million. Cooperation mode: joint venture.
IV. Analysis of economic benefits: upon completion of the Project, 300t clam, 40t penaeus penicillatus and 40t red-foot crab can be produced, 10 million abalones can be cultivated and 30t adult abalone can be sold every year. The output value will be up to RMB 8 million.
V. Preliminary work: site selection has been preliminarily completed.
VI. Project organizer: People's Government of Houlong Town
VII. Contact person: Lin Pingkun
Tel: 0595-87731560 Fax: 0595-87731556
63. Third Affiliated Hospital of Fujian Medical University
I. Project description: the hospital is planned to cover an area of 276mu with total building area of
II. Construction reasons and conditions: the project can improve medical treatment and provide health care service and has received the vigorous support from Wu Mengchao, an academician who is the founder of liver surgery in
III. Total investment: RMB 2,172 million.
IV. Analysis of economic benefits: annual outpatient service is planned to be 800 thousand - 1 million person-times, annual patient number of hospitalization 40,000-50,000 person-time and annual surgical volume 30,000 person-times.
V. Preliminary work: the project (the first-phase engineering) is listed as a provincial key construction project. The foundation was laid in May 2011. At present, the first-phase engineering is under construction. The Proposal of second-phase engineering has been approved by Fujian Development and Reform Commission and the feasibility study report has been submitted for approval.
VI. Project organizer:
VII. Contact person: Xu Xiaoqing
Tel: 13959115313 Fax: 0591-22862286
Email:fsyy@mail.fjmu.edu.cn
64. Huangshi Commercial Logistics Park in Putian
I. Project description: the project is planned to cover an area of 11,000mu. It is proposed to build an arts and handicrafts town, a shoes & garment town, a Straits International Trade Town, a 4S motor town, a building materials & home furnishing town, a distribution center of SINOPHARM Group and Zhongmin Medicine Trade Co., Ltd., a comprehensive logistics center, a commercial office cluster, a theme commercial area and the like.
II. Construction reasons and conditions: the project enjoying favorable geographic location is planned to be built into a modern commercial logistics park mainly integrating commercial exhibition and selling and logistics & distribution, equipped with residence and public service. The Project will build distinct functional zones and complete supporting public utilities in a beautiful and convenient living environment.
III. Total investment: RMB 10 billion. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: after the project is put into production, the annual trading volume will reach RMB 100 billion.
V. Preliminary work: within the Park, China Putian Arts and Handicrafts Town and the shoes & garment town have formally started to operate; the Straits International Trade Town is under construction; the auto park, building materials & home furnishing town, the logistics center of Luyan Pharmaceutical, the storage & logistics center of SINOPHARM Group and Zhongmin Medicine Trade Co., Ltd., Jin Jiang Hotel and the like are to be constructed. Besides, ancillary facilities such as roads are gradually being improved.
VI. Project organizer:
VII. Contact person: Huang Meifang
Tel: 0594-2388110, 13950745658 Fax: 0594-2336359 Email: Lctz2388110@163.com
65. Second-Phase Real Estate Project in Mazu Town, Putian City
I. Project description: it is planned to develop a project covering 1,500mu for commercial residence, office, club, hotel and public facilities with building area of
II. Construction reasons and conditions: the development of
III. Total investment: RMB 5 billion. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: upon the advantage of hometown of Mazu,
V. Project organizer: Department Bureau of North Bank Economic Development Zone
VI. Contact person: Guo Qingxing
Tel: 13905043008 Fax: 0594-5952956
Email:ba5952968@163.com
66. Tourism Resource Development Project of Xianyou County
I. Project description: it is planned to build a place for dream praying ceremony as Xianyou is named as "
II. Construction reasons and conditions: Xianyou possesses rich tourism resources and has four major scenic spots including
III. Total investment: RMB 1,825 million. Cooperation mode: cooperation, joint venture or exclusive investment. Separate investment in single engineering is also allowed.
IV. Preliminary work: planning and site selection has been completed.
V. Project organizer: Investment Invitation Bureau of Xianyou County
VI. Contact person: Zhu Weicai
Tel: 18760528263 Fax: 0594-8261234
Email: Fjxytz@163.com
67. Putian Marine Products Refrigeration and Cold Chain Logistics
I. Project description: it is planned to build a collective transaction center and cold chain logistics base for marine products like abalone, kelp, etc.
II. Construction reasons and conditions: Xiuyu District has rich marine resources with the total costal cultivating area of 54,283.96 hectares producing marine products like fish, shrimp, crab, kelp, etc. To promote the healthy and long-term development of marine product market in Xiuyu District, it is urgent to build a marine products refrigeration and cold chain logistics project in Xiuyu District. And it is planed to adopt the LNG cold energy construction and cold chain logistics base.
III. Total investment: RMB 200 million. Cooperation mode: joint venture, cooperation or exclusive investment.
IV. Preliminary work: initial design has been completed.
V. Project organizer:
VI. Contact person: Huang Xiaozhi
Tel.: 0594-5857733,13860932200
Fax: 0594-5870135 Email: 5857733@163.com
68. Creative Industries Center of Cross-strait Marine Culture in Meizhou Island
I. Project description: the project covers an area of 2,900mu, including 1,000mu reclaim land. The Project plans to build cross-strait artistic creation base, Mazu belief museum, music making workshop, Mazu cultural museum park, cross-strait marine hairdressing and health preservation hall, international cruise terminal, yacht club, finishing household folk tour, sea fishing center, island botanic gardens, Meizhou island impression art center, etc.
II. Construction reasons and conditions:
III. Total investment: RMB 2.3 billion. Cooperation mode: cooperation, joint venture or exclusive investment. Separate investment in single engineering is also allowed.
IV. Preliminary work: planning and site selection have been completed.
V. Project organizer: Meizhou Island Administrative Commission
VI. Contact person: Zheng Wengui
Tel.: 0594-5094335, 13850201399 Fax: 0594-5092031 Email: Zlfpt@126.com
69. Auto Parts Industrial Park in Changting County
I. Project description: the planned area of the Project is 5,000mu. Main products include: axle, gear box, interior trim parts of auto, auto mould, auto diverter, auto lighting, auto instrument and the like. It is proposed to be developed into a production base for domestic and overseas market of complete vehicle accessories and auto parts.
II. Construction reasons and conditions: at present, there are more than 100 enterprises producing special vehicles, cargo truck and light/heavy truck in
III. Total investment: RMB 600 million. Cooperation mode: cooperation.
IV. Analysis of economic benefits: the annual output value will be RMB 1.8 billion and the profit will be RMB 180 million.
V. Preliminary work: the planning and design have been completed.
VI. Project organizer: Changting Bureau of Machinery and Electronics Industry
VII. Contact person: Lai Honglu
Tel: 13806995192
70. Longyan Exhibition City
I. Project description: the planned area of the project is 900 mu, including 380mu for the first-phase engineering with total building area of
II. Construction reasons and conditions:
III. Total investment: RMB 1.3 billion. Cooperation mode: BT or cooperation.
IV. Preliminary work: woodland vetting procedures of Fujian Forest Department and the land approval procedures of Fujian Provincial Government have been handled for the planned first-phase land of the exhibition city. The Project designer has been selected and the design plan is now being improved. Meanwhile, site leveling and bid inviting for supervisory unit have been completed.
V. Project organizer: Longyan Exhibition Co., Ltd.
VI. Contact person: Ou Wenlong
Tel: 13906070892
71. Longyan Central Soviet Areas Park Construc- tion Project
I. Project description: covering an area of 1,308 hectares, the Project takes the central soviet areas spirit as connotation and the red culture as the mainline, composites red culture, Hakka culture and folk culture, and builds up a comprehensive cultural park integrating ecotourism, mountain leisure and cultural experience as a whole.
II. Construction reasons and conditions: by modeling the central soviet areas theme culture and implanting of leisure industrial economy, the Project aims at building up a comprehensive park representing urban humanistic spirit, beautiful ecological environment and good economic format to comprehensively promote the urban cultural image, perfect the urban function and promote the urban industrial and economic development.
III. Total investment: RMB 800 million.
IV. Project organizer: Longyan Municipal Development Group Co., Ltd.
V. Contact person: Lin Jie
Tel.: 0597-2991219, 18906070105
72. General Hospital in Gaokan New Town, Yongding County
I. Project description: the project plans to build up a balanced and fully developed general hospital in all strengths by building a general ward building, outpatient service building, medical laboratory & office building and introducing excellent medical scientific talents and advanced equipment with 400 designed sickbeds and 5 ambulances.
II. Total investment: RMB 80 million. Cooperation mode: exclusive investment or joint venture.
III. Preliminary work: planning and site selection have been completed.
IV. Project organizer: Urban Construction & Development Co., Ltd. in
V. Contact person: Chen Shenghu
Tel.: 13906976110
73. Development Project of Heping Ancient Town Scenic Area in Shaowu City
I. Project description: including restoration of watchtower in east and north gates, Heping Academy and Government Office of County Magistrate Assistant, facade repair of Heping Street and Dongmen Street, construction of Beimen Service Center, etc.; further planning projects such as removal, construction and fa?觭ade repair of Nanmen Tourism Service Center; development of 16 major attractions in Heping Town; construction of a 500mu international resort integrating leisure, vacation and shopping
II. Construction reasons and conditions: established over 4,000 years ago,
III. Total investment: RMB 217 million.
IV. Analysis of economic benefits: the annual sales revenue will be RMB 110 million, the profit will be RMB 33 million and in the payback period will be 7 years upon completion of the Project.
V. Preliminary work: Protection and Renovation Plan for
VI. Project organizer: Tourism Bureau of Shaowu City
VII. Contact person: Zhang jinhua
Tel: 13706013018
74. Tianbao Commerce Park in Zhangzhou
I. Project description: with an overall planned area of 6,000mu, of which 1,500 for Phase I, the project plans to introduce professional market of trade and logistics or construct the urban commercial complex.
II. Construction reasons and conditions: the
III. Total investment: RMB 3 billion. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: it is expected that the annual tax revenue will reach RMB 100 million.
IV. Preliminary work: regulatory plan has been completed.
VI. Project organizer: People's Government of Tianbao Town
VII. Contact person: Lu Qingyong
Tel: 13605083244
75. Sandu'ao Coastal Tourism Development Project
I. Project description: it is planned to construct Jiaotou Tourist Service Center and Central Pier, Sandu Island Ancient Relics Scenic Spot, Doumu Island Scenic Spot, Qingshan Island Tourist Resort; Jigongshan Island Scenic Spot, Ganlan Island Scenic, seafood fishing city, real estates of coastal landscape, luxurious marine cruises, marine fishing recreation areas, Qingshan Island Holiday Resort, Ganlan Island Yacht Club, Jigongshan Island Mariners' Club and the like.
II. Construction reasons and conditions: Sandu'ao, the only "
III. Total investment: RMB 2.2 billion. Cooperation mode: exclusive investment or cooperation.
IV. Analysis of economic benefits: upon its completion, the annual tourist reception will be about 300,000 person-times, the income of each item will be more than RMB 300 million and the payback period will proximately be eight years.
V. Preliminary work: Tourism Development Plan of Jiaocheng District and Regulatory Plan of Concept of Tourism Scenic Plots of Jiaocheng District.
VI. Project organizer: Tourism Bureau of Jiaocheng District
VII. Contact person: Gong Qingtuan
Tel: 0593-2826122, 13950596066
76. Tianxing Mountain National Forest Park in Pingnan County-Tourism Development Project of Longjing Bridge Scenic Spot
I. Project description: it is planned to expand the tourist highway
II. Construction reasons and conditions: with an area of 1,152 Hectare, Longjing Bridge Science Spot covers more than 50 natural landscapes such as Tianxing Mountain, Liancui Ridge, Pinus Taiwanensis Forest, Daxian Rock, Huoshao River and the like, forming a beautiful scenic picture with unique mountain, river, forest and spring landscapes enhancing each other's beauty.
III. Total investment: RMB 303.48 million. Cooperation mode: joint development.
IV. Analysis of economic benefits: the annual business income of the project under normal operation is estimated to be RMB 66,084,400, and the annual profits will be RMB 22,198,400 (after income tax).
V. Preliminary work: State Forestry Bureau has approved to build the Tianxing Mountain National Forest Park; the preparation of General Plan of National Forest Park has been complied, the approval and detailed plan of which is underway; and other works are being arranged.
VI. Project organizer: Fujian Dachang Hydropower Group Co., Ltd.
VII. Contact person: Lin Wei
Tel: 0593-3322468, 13959339933
77. Construction Project of Ninghua County Modern Logistics Center between Fujian and Jiangxi
I. Project description: covering an area of 1,000mu and total construction area of
II. Construction reasons and conditions: among the six counties along the borders between Fujian and Jiangxi, Ninghua County, which is located in the middle of the this border, has the widest area and the largest populations, so it becomes the intersection point of the economic zones between the west of Fujian and south of Jiangxi, and becomes one of the important material distribution center. Along with the shaping of the completed frame system of Ninghua transport network, it is necessary to build a modern logistic center in
III. Total investment: RMB 1 billion.
IV. Analysis on expected economic benefits: the annual revenue will be RMB 1.3 billion, the profit will be RMB 120 million and the investment will be recovered in 8.3 years after the Project being completed and putting into operation.
V. Preliminary work: the feasibility report has been compiled.
VI. Project organizer: Economic and Trade Bureau of Ninghua County
VII. Contact person: Zhang Fahua
Tel: 0598-6824651, 13507552016
78. Taxus Chinensis Cultural Creative Industrial Park Project in Mingxi County, China
I. Project description: covering a building area of
II. Construction reasons and conditions:
III. Total investment: RMB 500 million.
IV. Analysis of economic benefits: upon completion and operation, the Project will achieve an annual rate of return of 18% and the pay back period (static) will be 5-6 years.
V. Preliminary work: the pre-project planning has been completed with 30,000mu taxus chinensis var mairel bases built up and 1 million bonsais planted.
VI. Project organizer: Forestry Bureau of Mingxi County
VII. Contact person: Lin Baoyun
Tel.: 1360596919
79. Huangchao Ecological Leisure & Tourism Resort in Nanan City
I. Project description: the project plans to build and develop a Huangchao tourism scenic spot, a sports park and a tourism holiday villa with an area of
II. Construction reasons and conditions: the project aims at promoting the tourism industry development of
III. Total investment: RMB 900 million. Cooperation mode: joint development.
IV. Project organizer: Nanan Development and Reform Commission
V. Contact person: Li Changqing
Tel.: 13959865858
80. Quanzhou Strait Luggage Logistics Mall
I. Project description: in the first phase, the project covers an area of 137mu, and the total construction area is
II. Construction reasons and conditions: currently, Quanzhou has more than 1,,000 luggage manufactures with an annual output value of over 10 billion, being the main production base of the whole province, even for the entire country. Once completion, the modern Quanzhou Strait Luggage Logistic Mall will become the biggest wholesale mall for raw and auxiliary materials of luggage in southeast of
III. Total investment: RMB 1.2 billion. Cooperation mode: using rents or sales to introduce related cooperates to run business such as wholesales of raw and auxiliary materials for luggage, finished products exhibition, research and training and the like in the mall.
IV. Analysis on expected economic benefits: it is estimated that more than 3,000 businesses come from the whole country (including
V. Preliminary work: the procedures such as project identification, planning scheme, environmental impact assessment and the like have been submitted and approved, and the land using in first phase has conducted "bidding, auction and listing" after resettlement. The pile foundation construction is carried out now.
VI. Project organizer: Quanzhou Strait Luggage Logistic Mall Co., Ltd.
VII. Contact person: Du Xuhui
Tel.: 0595-22508529, 13358585805
81. National Basketball Training Base in Nan'an City
I. Project description: the planning area is 53.5 hectares. Base construction includes the competition hall, training hall and supporting facilities such as ground track field, outdoor basketball court, tennis court, swimming pool, athlete's apartment, sports hotel, office building, body quality training hall and group construction center and so on.
II. Construction reasons and conditions: basketball is a traditional and advantageous sport event in Nan'an, which has more than 200 thousand basketball athletes. Nan'an City has long been the major competition field course of Fujian Women Basketball Team, and it has held the basketball game of the 8th National Farmers' Sports Meeting. After completion of the "National Basketball Training Base", the national team and sports teams of other provinces will be attracted here for training.
III. Total investment: RMB 647 million. Cooperation mode: exclusive investment, joint venture or cooperative construction and stadium operation.
IV. Preliminary work: planning and design of the project are underway. 746mu land has been acquired and leveling of partial plots has been completed. Nan'an
V. Project organizer: Bureau of Culture and Sports of Nan'an City
VI. Contact person: Chen Xinxin
Tel: 13506037297
82. Xiamen Aviation Logistics Operation Service Center
I. Project description: the total building area is about
II. Construction reasons and conditions:
III. Total investment: RMB 350 million.
IV. Analysis of economic benefits: the financial internal rate of return will be 9.5%, the profit rate of investment 10.8% and the static payback period on investment 10.2 years.
V. Preliminary work: roof capping of building was completed in December 2011, and at present, construction of curtain wall and internal/external decoration are in process. The Project will be completed in the second half of 2013.
VI Project organizer: Xiamen Free Trade Zone Aviation Logistics Park Construction Co., Ltd.
VII. Contact person: Lin Yimei
Tel: 13606079872, 0592-5707579
Fax: 0592-5706660-6589
E-mail:lym@iport.com.cn
83. Financial Center across Taiwan Straits
I. Project description: the project is planned to cover an area of
II. Construction reasons and conditions: in 2010, Several Opinions of the State Council of the PRC on Supporting Fujian Province to Accelerate the Building of the Economic Zone on the West Coast of the Taiwan Straits was issued, and "Establishing regional financial service center across Taiwan Straits, and pre-implementing and pre-testing some significant reform measures in financial application" was formally approved. In 2011, construction of economic zone on the west coast of Taiwan Straits was specially put forwarded in Outline of the "12th Five-Year Plan", facilitating the construction of the regional financial service center across Taiwan Straits in
III. Total investment: RMB 175 billion.
IV. Analysis of economic benefits: a national grade regional financial service center across Taiwan Straits will be established.
V. Preliminary work: some plots have been exploited for construction, and part of projects introduced is undergoing listing procedures.
VI. Project organizer:
VII. Contact person: Wang Yanyu and Feng Guangyu
Tel.: 0592-2667376, 0592-5722382
Fax: 0592-2667149,0592-5722385
Emai:wangruru@126.com,zsj@huli.gov.cn
84. Jimei Logistics Park
I. Project description:
II. Construction reasons and conditions: logistics industry is a pillar industry of
III. Total investment: RMB 550 million.
IV. Analysis of economic benefits: the total revenue from trade service, financial service, lease of office and storage equipment, transportation outsourcing, stamp tax and land use tax will reach RMB 360 million after the Project is put into production and increases to RMB 640 million in 5 years.
V. Preliminary work: land acquisition and prophase construction procedures are underway.
VI. Project organizer: Jimei State-owned Property Investment Co., Ltd.
VII. Contact person: Lin Huihong
Tel: 13950011788, 0592-6253258
85. Business Office Project of Xiang'an New Town CBD
I. Project description: the project, located in Xindian Town of Xiang'an District, covers an area of 1,000mu. In this project, the planned public service facilities include business office and city complex,
II. Construction reasons and conditions: Xiang'an possesses unique advantages of location and economic development in the progress of construction of western coast of Taiwan Straits and integrative development of
III. Total investment: RMB 1.6 billion.
IV. Analysis of economic benefits: land revenue of the Project will be about RMB 1.6 billion.
V. Preliminary work: three supplies (supply of water, electricity and road), and one leveling and urban facilities are under construction.
VI. Project organizer:
VII. Contact person: Luo Mingqing
Tel: 13860108688, 0592-7889892
Fax: 0592-7889078 Email:xmxacdc@vip.163.com
86. Haicang Bonded Port
I. Project description: the project occupies
II. Construction reasons and conditions: this project was approved by the State Council on Jun.5, 2008. It covers an area of
III. Total investment: RMB 5 billion.
IV. Analysis of economic benefits: according to national policies, settled enterprises are entitled to enjoy relevant preferential policies and foreign exchange policies in the bonded area, export processing zones and the bonded logistics park.
V. Preliminary work: operation in customs - closing status of the first and second phase Project, and the third phase Project is being under construction.
VI. Project organizer: Haicang District Government and Haicang Bonded Port Administrative Committee
VII. Contact person: Xie Jin'e
Tel.: 0592-6896675, 13950010212 Fax: 0592-6895998 Email: xieje@haitou.cn
87. Commercial Logistics Park in Putian Hushi Railway Station
I. Project description: the first phase engineering covers an area of 1,000mu. It is planned to build a comprehensive central logistics park integrating specialized commercial wholesale logistics center, storage, information management, supplier management inventory, domestic distribution and international shipping agency center and management center of goods on consignment.
II. Construction reasons and conditions: Hushi Railway Station plays an important pivotal role with remarkable location advantages, thus providing good conditions for rapid and efficient operation of logistics. To satisfy human's needs in life and improve people's living standard, it is quite necessary to build a commercial logistics park in Hushi Railway Station.
III. Total investment: RMB 720 million. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: the Project is a long term investment project with low risk and short payback period.
V. Preliminary work: the feasibility report is being compiled.
VI. Project organizer:
VII. Contact person: Yang Zhi
Tel.: 0594-5850988 Fax: 0594-5870135
Email: 5857733@163.com
88. Logistics Base of Xiuyu National Processing Demonstration Area for Timber Trade in Putian
I. Project description and site selection: the floor area is 100mu and total building area is
II. Construction reasons and conditions: with the continuous development of Xiuyu National Processing Demonstration Area for Timber Trade, the backward logistics level has become a bottleneck for further development of processing industry of forest products. A modern logistics system of processed forest products connecting southern provinces can further improve the auxiliary facilities of timber processing zone, thus promoting virtuous cyclic development of forest product processing and logistics.
III. Total investment: RMB 200 million. Cooperation mode: joint venture, cooperation or exclusive investment.
IV. Analysis of economic benefits: upon analysis on the development status and prospect of timber processing zone, it is shown that the Project is of a good market prospect.
V. Preliminary work: initial design has been completed
VI. Project organizer:
Tel: 0594-5857733
Fax: 0594-5870135 E-mail: 5857733@163.com
89. Large Cold Storage Project of Fruit, Vegetable & Tea Trade Center on West Coast of Taiwan Straits
I. Project description: it is proposed to build an auxiliary project of Fruit,
II. Construction reasons and conditions: as a major city of agricultural and sideline products, Jian'ou City abounds in agricultural products. The Project, as the auxiliary project of Fruit, Vegetable & Tea Trade Center on West Coast of Taiwan Straits, will create good conditions for sales and refreshment of local agricultural products and distribute the fruit, vegetable and tea across the country after the trading in the trade center, which is beneficial for industrialized development of the production of local special agricultural products.
III. Total investment: RMB 200 million. Cooperation mode: joint venture, cooperation or transfer.
IV. Analysis of economic benefits: the average annual operating revenue is estimated to be RMB 52.8 million; average annual profits RMB 34.83 million and average annual after-tax profits RMB 26.13 million with FIRR of 17.2%. Besides, the investment payback period will be 7.6 years.
V. Preliminary work: project initiation, pre-examination for land, project planning, feasibility study report, water and soil conservation program, preliminary environmental impact assessment, geological disaster appraisal, construction plan and survey and approval for construction land have been finished.
VI. Project organizer: Fujian Hailü Agricultural Development Co., Ltd.
VII. Contact person: Lei Luxin
Tel: 13960603566, 0599-3715088 E-mail:FJHL61@QQ.COM
90. Tourism Development Project of Pucheng Kuangshan Mountain Scenic Spot
I. Project description: the project is divided into three phases: at the first phase, folk vacation tour area and Kuangshan Mountain National Forest Park as well as the auxiliary facilities thereof will be built; at the second phase, Kuanghu Lake Leisure Tourism Area and Yangmei Mountain Rural Agricultural Sightseeing Resort will be built, including rural environmental remediation, agricultural sightseeing park, recovery of Li's Ancient Folk Houses and agritainment training project. At the last phase, Gaofang Comprehensive Tourist Service Area and Liantangban Rural Tourism Resort will be built.
II. Construction reasons and conditions: Pucheng is located in the north of
(Longquan-Pucheng Expressway), Pucheng has become an important transport junction connecting the north and the south.
III. Total investment: RMB 200 million. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the annual revenue from tourism will be RMB 300 million and the tax revenues will be increased by RMB 6 million after the completion of the Project. The investment payback period is expected to be 1.5 years.
V. Preliminary work: tourist highway subgrade has been widened; and the pre-feasibility study report of Kuangshan Mountain Scenic Spot, the declaration of "Forest Home" and resource protection work of the scenic spot have been completed.
VI. Project organizer: Tourism Bureau of Pucheng County
VII. Contact person: Li Minxing
Tel: 0599-2847639, 13509527299
E-mail: PCLY2847639@163
91. Shaowu Hot Spring Resort
I. Project description: the floor area and building area of the Project are 100mu and
II. Construction reasons and conditions: Shaowu owns rich geothermal resources. The outlet temperature of proved hot spring is about
III. Total investment: RMB 160 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the annual operation revenue will be RMB 76.2 million, the profit will be RMB 34.3 million and payback period will be 4.6 years upon the completion of the Project.
V. Preliminary work: pre-planning has been completed.
VI. Project organizer: Shaowu Development and Reform Commission
VII. Contact person: Yang Meijuan
Tel: 0599-6233716, 18960607186
92. Development Project of Donggong Mountain Provincial Scenic Spot in Zhenghe County
I. Project description: it is proposed to build
II. Construction reasons and conditions: Donggong Mountain Scenic Spot, covering an area of
III. Total investment: RMB 400 million.
IV. Preliminary work: overall planning has been finished; the scenic spots such as
V. Project organizer: Tourism Bureau of Zhenghe County
VI. Contact person: Liu Weiwen
Tel: 18965370916 Fax: 0599-3457601
93. Construction Project of Five-star Hotel in Zhenghe County
I. Project description: it is proposed to build a five-star tourism hotel integrating guest room, restaurant, conference room, office room and recreation facilities with a floor area of about 50mu.
II. Construction reasons and conditions: at present, there is still no star hotel in
III. Total investment: RMB 150 million. Cooperation mode: exclusive investment.
IV. Analysis of economic benefits: the annual sales revenue will be RMB 40 million and the operating profit will be RMB 15 million with the investment payback period of 10 years upon completion of the Project.
V. Preliminary work: site selection and planning of the Project has been completed.
VI. Project organizer: Tourism Bureau of Zhenghe County
VII. Contact person: Liu Weiwen
Tel: 18965370916 Fax: 0599-3457601
94. Zhangzhou Lin Yutang Cultural Park
I. Project description: the Park is themed on "World's Yutang, Yutang's Home" with a floor area of 44.7 hectares. It is proposed to build one belt: boardwalk sightseeing belt and six areas: Yutang Memorial Area, Culture Enjoyment Area, Life Enjoyment Area, Living Enjoyment Area, Former Residence Area and Pilgrimage Area.
II. Construction reasons and conditions:
III. Total investment: RMB 232 million. Cooperation mode: joint venture or cooperation.
IV. Analysis of economic benefits: it is expected that the annual tourists will be up to 1 million and the annual revenues from tourism will be over RMB 30 million after completion of the Project.
V. Preliminary work: conceptual planning and design of the Project has been finished by Shui Mu Qing Hua (Xiamen) Architecture Planning and Design Co., Ltd.; and the construction of boardwalk sightseeing belt (Phase I),
VI. Project organizer: People's Government of Tianbao Town, Xiangcheng District, Zhangzhou
VII. Contact person: Shen Xiaohui
Tel: 0596-2540842, 13960034789
95. Complex Project of Cultural Tourism in Zhangzhou Ancient Town
I. Project description: with a total planning area of about 1 square kilometer, the Project focuses on forming a comprehensive protection pattern of "one ring, three zones". "One ring" refers to a landscape zone with recovery of
II. Construction reasons and conditions: the historical block, with a total planning area of about 1 square kilometer, lies in the north bank of
III. Total investment: RMB 2 billion. Cooperation mode: cooperation.
IV. Analysis of economic benefits: after construction, the tourists received annually will be above 1.2 million, with annual revenues of over RMB 40 million.
V. Preliminary work: the Project has been delegated to Zhejiang Hitorical Architecture Design & Research Institute for overall planning.
VI. Project organizer: Administrative Commission of Zhangzhou Historical Block
VII. Contact person: Li Haiguang
Tel:13605001516
96. Cross-Straits Aquatic Product Processing Park and Eastern Coast Logistic Center Project
I. Project Description: to develop Dongshan cross-Straits distribution center of aquatic product processing and trading platform of aquatic product with advantages of technology, economy and trade communication towards
II. Construction reasons and conditions: in Jan, 2010,
III. Total investment: RMB 500 million. Cooperation mode: BT or BOT.
IV. Analysis of economic benefits: project construction achieved the industrical development goal of RMB 10 billion output value and RMB 1.5 billion revenues.
V. Preliminary work: at present, aquatic product wholesale markets like Haikui and the Star of Sea, which have been developed to a certain scale, will become trading platform of cross-Straits aquatic product and trading base that connects Southeast Asia and large and medium sized cities in
VI. Project organizer: Headquaters of Aquatic Product Processing & Districbution Base
VII. Contact person: Li Tianfu
Tel: 13960136708
97. Subsidiary Agricultual Product and Featured Product Processing Base in Penghu, Yongchun County
I. Project Description: Developing a subsidiary agricultual product and featured product processing base with a planning area of 72.2 hectares.
II. Construction reasons and conditions: with the opening of Quansan Expressway (Quanzhou-Sanming Expressway), Penghu, the pilot town of comprehensive reform of Quanzhou small towns and subcenter of
III. Total investment: RMB 200 million.
IV. Analysis of economic benefits: with low-carbon economy as its development path and subsidiary agricultual product and featured product processing industry as its keypoint, the Project introduces enterprises with a certain scale, high quality and good economic returns. By estimation, high economic returns will be achieved after construction.
V. Preliminary work: by far, preliminary work of infrastructure construction including land acquisition, demolition, drainage, sewage disposal, road, communication and electricity has been completed.
VI. Project organizer: People's Government of Penghu County
VII. Contact person: Zheng Bin
Tel: 13505930873
98. Ecotourism Development in Heshi Town, Luojiang District
I. Project Description and Construction Scale: the construction of entrance service area, sight seeing area, resort, fishing center, reception service center of rural tourism and other ancillary facilities.
II. Construction reasons and conditions: the land has high development value. Located in
III. Total investment: RMB 150 million.
IV. Analysis of economic benefits: the financial internal rate of return will be 4%, the profit rate of investment 10% and the investment payback period 9 years.
V. Preliminary work: site selection of the Project has been completed.
VI. Project organizer: People's Government of Heshi Town, Luojiang District
VII. Contact person: Huang Jiaqing
Tel: 13559621710 Fax: 0595-22033016
99. Xiangong Mountain Ecotourism Resort in Luojiang District
I. Project description: proposed constructions including hotels, mountain resort, ropeway, herbarium garden and zoo.
II. Construction reasons and conditions: supported by
III. Total investment: RMB 300 million. Cooperation mode: exclusive investment, joint venture or contracted management.
IV. Preliminary work: the mountain gate, the road to the mountain gate and the construction of South & North Pavillions has been completed. Preliminary planning of the resort is in progress.
V. Project organizer: Majia Town Government of Luojiang District
VI. Contact person: Lai Yongsui
Tel: 13905960699 Fax: 0595-22080099
100. Yunhe Valley Scenic Spot Project in Waishan Village, Yongchun County
I. Project description: in accordance with the planning, the scenic spot will construct ancillary facilities including the reception center, the Yunhe Villa, an ecological parking lot, a landscape lake, the tourist artery around the region and the ecological agriculture tourism park.
II. Construction reasons and conditions: the major scenic spot covers 350 hectares, with a depth of
III. Total investment: RMB 150 million.
IV. Analysis of economic benefits: with the perfection of ancillary facilities for eating, accommodation, shopping and recreation, the reception ability and scale of the scenic spot will be further developed. The annual increased tourist will be above 200 thousand with tourist income reaches RMB 30 million.
V. Preliminary work: the expanding transformation of roads from Provincial Road Sanjiao to the scenic spot, afforestation and beautification of the district, a
VI. Project organizer: People's Government of Waishan Village,
VII. Contact person: Yu Ruyi
Tel: 13805937705, 0595-23711009
Fax: 0595-23711081 E-mail: ycwszf@163.com
101. Quangang "Archaized Pavilion" Tourism Project at the Bank of the Batou River
I. Project description: considering the reconstruction of the drainage area of
II. Construction reasons and conditions: combined with the reconstruction of the drainage area of the Batou River and the plan to construct "Archaized Pavilion" Tourism Project at the Bank of the Batou River, it is of great significance to achieve the sustainable development of the region's economy and society, to promote the petrochemical bases and urban construction, the harmony between industrial enterprises and the surrounding residents.
III. Total investment: RMB 500 million. Cooperative form: exclusive investment, joint venture, cooperation, or BOT.
IV. Preliminary work: site selection has been preliminarily completed.
V. Project organizer: Development and Reform Bureau of Quangang District
VI. Contact person: Zhang Zhangshui
Tel.: 0595-87978796, 13960291850
102. Houlong Bay Surrounded by Quangang- Five-Mile Haisha Culture and Leisure Project
I. Project description: to construct business hotels, business centers, cultural entertainment centers, and leisure squares with a land area used for construction of
II. Construction reasons and conditions: with the opening-up of the passages along the sea and the dead end roads at the east sections of Yifeng Road and Nanlong Road, Houlong Bay is close to Meizhou Bay and is shaped by a moon,which has a superior geograghical position and a requisitioned land area including 1,000mu of sea area.
III. Total investment: RMB 300 million.
IV. Analysis of economic benefits:
V. Preliminary work: site selection has been preliminarily completed
VI. Project organizer: People's Government of Houlong Town
VII. Contact person: Lin Pingkun
Tel.: 0595-87731560, 13506016806
Fax: 0595-87731556
103. Tourism Area of Family Cai's Ancient Residential Buildings in Nan'an City
I. Project description: the planned area is 73 hectares. Landscape facilities like
II. Construction reasons and conditions: Cai's Ancient Residential Buildings, built during the period from Tongzhi reign of Qing Dynasty (1862) to the 3rd year of Xuantong reign, belong to key cultural relics under state protection. There are 16 relatively integrated buildings now, covering an area of
III. Total investment: RMB 161.3 million Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Analysis of economic benefits: according to the estimation, the average number of visitors per year will reach 280 thousand in the first five years and after five years, the number will come to 380 thousand while the average annual profit will be about RMB 14.84 million.
V. Preliminary work: Regulatory Plan for Tourism Development of Cai's Ancient Residential Buildings has been formulated, and more than RMB 2 million has been invested by the municipal government for infrastructure construction projects, such as the maintenance and fire-proof equipment of partial ancient residential buildings, cement road and public toilets.
VI. Project organizer: Guanqiao Township People's Government
VII. Contact person: Chen Liushui
Tel.: 0595-86882101, 13906096300
104. Huaxun Asia-Pacific International Incubation Base in Changle City
I. Project description: the planned land area is 500mu with a floor area of
II. Construction reasons and conditions: make use of internationalization advantage of Huaxun Group and foster ecological environment for innovative enterprise growth and cluster. The Project is to develop international cooperation channel in Asia-Pacific areas, establish technological innovation union and investment union in Asia-Pacific areas, and build technical cooperation and discussion platform, software and information service outsourcing platform, public technology support platform and scientific achievements trading platform.
III. Total investment: RMB 3 billion. Cooperation mode: share investment.
IV. Analysis of economic benefits: the newly increased annual revenue will be RMB 4 billion, with tax revenue being RMB 150 million.
V. Preliminary work: approval procedures of Huaxun Asia-Pacific International Incubation Base are underway, and key provincial project has been declared.
VI. Project organizer: Huaxun (
VII. Contact person: Lin Shen
Tel: 13509376626 Fax: 0591-88033633
105. Putian Urban Rapid Transit System
I. Project description: the line is planned to be about
II. Construction reasons and conditions: the urban population of
III. Total investment: RMB 25 billion. Cooperation mode: joint venture, cooperation or entrusted management, etc.
IV. Analysis of economic benefits: the public transport travel people of Putian are predicated to be 2,093,000 person-time/d, including 837,200 person-time/d for railway transport and 1,005,000 person-time/d for railway passenger flow. Therefore, the Project has good economic and social benefits.
V. Preliminary work: planning has been completed.
VI. Project organizer: Putian Development & Reform Commission
VII. Contact person: Cai Yunying
Tel.: 0594-2382311, 13905049316
Fax: 0591-2298744 E-mail: j3x001@163.com
106. Putian Airport Construction
I. Project description:
3,300mu in recent period and 3,750mu in the future.
II. Construction reasons and conditions: Putian Airport is quite necessary for promoting coordinated development of the region on the west bank of Taiwan Straits, for perfecting Fujian comprehensive transportation system, for carrying forward Mazu Culture in order to promote the work in Taiwan, for improving the characteristic economy in Putian, for integrating Putian tourism into "tourism on the west bank of Taiwan Straits", and for strengthening national defense capacity.
III. Total investment: RMB 850 million. Cooperation mode: exclusive investment, joint venture or cooperation.
IV. Preliminary work: Site Selection Report of Airport in Putian, Fujian, Design Plan of Flight Procedure during Site Selection of Airport in Putian, Fujian, Necessity Analysis on Airport Construction in Putian, Fujian and Study on Development Strategy of Airport in Putian, Fujian have been completely prepared.
V. Project organizer: Putian Development & Reform Commission
VI. Contact person: Cai Yunying
Tel.: 0594-2382311,13905049316
Fax: 0594-2298744 E-mail: j3x001@163.com
107. Shacheng Central Fishing Port in Ningde City
I. Project description: construction of 1,500mu fishing port wharf and supporting facilities.
II. Construction reasons and conditions: Shacheng port is deep and wide with convenient transportation and rich fish resources, making it the ideal place for constructing a fishing port.
III. Total investment: RMB 80 million.
IV. Analysis of economic benefits: BT investment will be adopted and the investment payback period will be 6 years.
V. Preliminary work: the First-Class Fishing Port in
VI. Project organizer: People's Government of Shacheng Town
VII. Contact person: Chen Xiaolong
Tel.: 0593-7581436,l3950561719 Fax: 0593-7581154
108. Mt.
I. Description: The implementation of main project design and construction shall be in accordance with national second-class standard, and it should include the complex building integrated with hotel and restaurant, waiting building, office building and public park, long-distance, short-distance, countryside and public transportation and taxi in the station ground, and a second-class bus station which is an effective auxiliary to the planned hub of railway passenger transport.
II. Reasons and conditions: With Pucheng-Nanping, Wyi-Shaowu, Ningde-Wuyi and Songxi-Jian'ou highway being open to traffic, the expansion of Mt. Wuyi Airport, especially the construction of Jingfu high-speed rail which will expand to the section between Fuzhou and Mt. Wuyi, the external traffic condition of Mt. Wuyi can, to a large extent, be improved and make it become a key transportation hub to bridge the south and the north.
III. Total investment: RMB150 million. Cooperation form: Exclusive investment or joint venture.
IV. Analysis on economic benefits: It is estimated that the income will increase by RMB 100 million annually after the project is completed and put into operation, and the profit will be RMB 50 million and the investment will be paybacked in 3 years.
V. Preliminary work: The site selection and pre-feasibility study have been done.
VI. Project organizer: Project Office of Wuyi City
VII. Contact person: Hu Bijiang
Tel: 13905994766 Fax: 0599-5317866
Email: 5134xmb@163.com
109. Construction Project of Northern Section of Jiangjun Avenue of Yunxiao
I. Project description: the two-way avenue to be constructed is
II. Reasons and conditions: the northern section of
III. Total investment: RMB 269.05 million. BT mode is planned to be adopted for attracting investment.
IV. Preliminary work: survey and design have been carried out.
V. Project organizer: Construction Bureau of Yunxiao County
VI. Contact person: Lin Zhenkun
Tel: 13605030033 Fax: 0596-8522488
110. Construction Project of Yunxiao County Section (Phase II) of Zhangzhou Coastal Avenue
I. Project description: the designed length is
II. Reasons and conditions: the construction of the Project plays an important role in taking advantages of tourism resources and port resources along the avenue, speeding up the development of port resources, perfecting transportation network, optimizing investment environment, developing port economy and fully implementing the strategies of "Port in City" and "Port in County". The conditions are ripe for the construction project.
III. Total investment: RMB 380 million. BT mode is planned to be adopted for attracting investment. BT mode is adopted to tender for the construction.
IV. Progress of preliminary work: all the preliminary work has been completed and has been approved with the Document No. MFJT [2010]928. The preparation, examination and approval of preliminary design drawing of two phases and the preparation of working drawing have been completed.
V. Project organizer: Yunxiao County Luda Road Construction Co., Ltd
VI. Contact person: Wu Wenxian
Tel: 13605048008
111. Xinan Harbor Railway Byline
I. Project description: the Xinan Harbor Railway Byline is planned to be constructed according to Class II Highway Standard with total length of
II. Construction reasons and conditions: the Project aims at connecting the Xinan Industrial Zone to the Wenzhou-Fuzhou Railway with great significance to developing the
III. Total investment: RMB 2 billion. Cooperation mode: BT and BOT.
IV. Preliminary work: the Byline Project has been listed into the medium and long-term plan of
V. Project organizer: The Railway Construction Preparation Office of Ningde
VI. Contact person: Yang Weijia
Tel.: 13859686588
112. Storage and Wharf Construction of Operation Zone of Hougang Village, Shacheng Town
I. Project description: a wharf apron is planned to be arranged near the -20 to
II. Construction reasons and conditions: the
III. Total investment: RMB 1 billion.
IV. Analysis of economic benefits: The annual output value will be RMB 2.5 billion and the profit and tax will be RMB 200 million.
V. Preliminary work: being planned.
VI. Project organizer: People's Government of Shacheng ,Town
VII. Contact person: Chen Xiaolong
Tel.: 0593-7581436,l3950561719 Fax: 0593-7581154
113. Zherong-Chengguan Transit Expressway in National Highway G104
I. Project description: the Expressway is planned to be
II. Construction reasons and conditions: the Project will greatly relieve the traffic pressure in old district of Zherong County, improve living and transportation safety for the public there, improve regional transportation conditions and investment environment and promote the economic development of Zherong County, especially the expansion of export-oriented economy.
III. Total investment: BT method will be adopted, and corresponding area of land will be circled for operation in Plot B of new district in the east of
IV. Preliminary work: the feasibility report of the Project has been completed, and project approval and preliminary work are under process.
V. Project organizer: Transportation Bureau of Zherong County
VI. Contact person: Chen Hui
Tel.: 0593-8363001, 13950562988
Fax: 0593-2272270 E-mail: j3x001@163.com
114. Marine Reclamation Construction Project in Sanyu Village, Ningde City
I. Project description: 8,000mu marine area along
II. Construction reasons and conditions: the Sanyu new district is located between
III. Total investment: RMB 1.2 billion.
IV. Analysis of economic benefits: the investment payback period will be 8 years.
V. Preliminary work: Planning on Regional Sea Areas Utilization for Construction has been prepared, and the use right of national sea area has been officially approved.
VI. Project organizer:
VII. Contact person: Zheng Lixin
Tel.: 13950572668
115. Highway Project in Meilie Industrial Park
I. Project description: the highway project in
II. Construction reasons and conditions: the highway in
III. Total investment: RMB 325.8 million. Cooperation mode: exclusive investment or joint venture.
IV. Analysis of economic benefits: the ENPV is RMB 72.79 million, EBCR 1.2659, EIRR 10.1%, Payback Period EN 18.83 years and the Payback Period 18 years.
V. Preliminary work: the proposal of the project has been submitted for approval, and the feasibility study report and Phase-II preliminary design have been approved in the review.
VI: Project organizer: Construction Headquarters of Meilie Industrial Park Highway of
VII. Contact person: Liu Lan
Tel:13605980210
116. Xiaocuo Branch Line of Expressway Network on the West Coast of the Taiwan Straits
I. Project description: the branch line is planned to be
II. Construction reasons and conditions: the construction of the Project will perfect the expressway network arrangement in Fujian Province and Quanzhou City, enhance comprehensive transportation junction and connection on the west bank of Taiwan Straits, get through the collecting and distributing channels from the Quangang Harbor to the interior provinces and expand the economic hinterland of harbor groups on the west bank of Taiwan Straits. Agreement on project construction has been reached through several coordination and verifications by the People's Government of Quangang District with related departments, who will actively engage in and support the Project.
III. Total investment: RMB 1.201 billion.
IV. Analysis of economic benefits: the financial internal rate of return will be 5.89%, financial net present value RMB 300,805,400, return on investment 7.6%, payback period 16.35 years and loan repayment period of project debt (including the construction period) 13.85 years.
V. Preliminary work: in November, 2011, the People's Government of Quangang District organized and held the primary examination meeting on engineering feasibility; in January, 2012, the design unit provided the revised draft and submitted it to the Quanzhou Municipal Higher Advisory Committee and Quanzhou Development and Reform Commission; and in February, 2012, the Quanzhou Development and Reform Commission transmitted the engineering feasibility report of the Project to the Fujian Development and Reform Commission for application and review.
VI. Project organizer: Traffic & Transportation Bureau of Quangang District,
VII. Contact person: Lin Jiaqiang and Lin Mingjian
Tel.: 0595-68110209, 13960339876 and 13959972001
Fax: 0595-87996200 E-mail: qgqjtjgcg@163.com
117. Daitou-Qiulu Section in Putian of Meizhou Bay-Chongqing Expressway
I. Project description: the total mileage of the Project is
II. Construction reasons and conditions: the Project is necessary for constructing fast track between
III. Total investment: RMB 4.341 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: when social discount rate is 8%, economic net present value (ENPV) will be RMB 1.516 billion and economic internal rate of return (EIRR) will be 11.47%.
V. Preliminary work: engineering feasibility of the Project and preliminary design has been approved and rough estimate of preliminary design has been examined; design document of construction drawing has been examined and revised; bidding document of roadbed construction supervision and test detection has been examined and revised by Provincial Expressway Construction Headquarters.
VI. Project organizer: Meizhou Bay-Chongqing Expressway Co., Ltd. of
VII. Contact person: Chen Zhonghui
Tel: 13905046289 Fax: 0594-2686614
E-mail: ptmygsgl@163.com
118. Qiulu-Wuxing Village, Xianyou Section in Putian of Meizhou Bay-Chongqing Expressway
I. Project description: the total mileage of the project is
II. Construction reasons and conditions: the Project is necessary for constructing fast track between
III. Total investment: RMB 4.795 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: when social discount rate is 8%, economic net present value (ENPV) will be RMB 2.045 billion and economic internal rate of return (EIRR) will be 11.81%.
V. Preliminary work: engineering feasibility of the Project and preliminary design has been approved and rough estimate of preliminary design has been examined; design document of construction drawing has been examined and revised; roadbed construction (A7-A12), supervision and test detection bidding document has been examined and revised by provincial Expressway Construction Headquarters.
VI. Project organizer: Meizhou Bay-Chongqing Expressway Co., Ltd. of
VII. Contact person: Chen Zhonghui
Tel: 13905046289 Fax: 0594-2686614
E-mail: ptmygsgl@163.com
119. Guanling, Fuding-Zherong Section of Multiple Track of Shenhai Expressway
I. Project description: the whole line of the Project is within
II. Construction reasons and conditions: the Project is of great significance for perfecting the expressway network layout of west coast of the Taiwan Straits, improving traffic capacity of coastal road, strengthening the ties between west coast of the Taiwan Straits and Yangtze River Delta, promoting economic development of northeastern Fujian Province, enhancing the capacity to deal with unexpected events (take natural disasters for instance) and improving the ability to guarantee the emergency traffic.
III. Total investment: RMB 2.717 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: when social discount rate is 8%, economic net present value (ENPV) will reach RMB 985 million and economic internal rate of return (EIRR) will be 11.39%.
V. Preliminary work: prior approval of engineering feasibility of the Project has been obtained with reply of provincial development and reform commission. Report on the energy-saving assessment of projects newly increased has been submitted and preliminary design document has been completed and submitted. Project Company is under preparation.
VI. Project organizer: Shenyang-Haikou Multiple Track Expressway Co., Ltd. of
VII. Contact person: Shao Maochan
Tel: 0593-2768127, 18959308080 Fax: 0593-2879670 E-mail: smc-888@sohu.com
120. Fu'an-Zhangwan Section of Multiple Track of Shenhai Expressway
I. Project description: the expressway is planned to be double-way four-lane expressway with total length of
II. Construction reasons and conditions: the project is of great significance for perfecting the expressway network layout of west coast of the Taiwan Straits, improving traffic capacity of coastal road, strengthening the ties between west coast of the Taiwan Straits and Yangtze River Delta, promoting economic development of northeastern Fujian Province, enhancing the capacity to deal with unexpected events (take natural disasters for instance) and improving the ability to guarantee the emergency traffic.
III. Total investment: RMB 3.63 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: when social discount rate is 8%, economic net present value (ENPV) will reach RMB 1.409 billion and economic internal rate of return (EIRR) will be 11.84%.
V. Preliminary work: prior approval of engineering feasibility of the Project has been obtained with reply of provincial development and reform commission. Report on the energy-saving assessment of projects newly increased has been submitted and preliminary design document has been completed and submitted. Project Company is under preparation.
VI. Project organizer: Shenyang-Haikou Multiple Track Expressway Co., Ltd. of
VII. Contact person: Shao Maochan
Tel: 0593-2768127, 18959308080 Fax: 0593-2879670 E-mail: smc-888@sohu.com
121. Fuding (Border of Zhejiang Province and Fujian Province)-Qinyu Section of Multiple Track of Shenhai Expressway
I. Project description: the expressway is built to be double-way four-lane expressway with total length of
II. Construction reasons and conditions: the project is of great significance for perfecting the expressway network layout of west coast of the Taiwan Straits, improving traffic capacity of coastal road, strengthening the ties between west coast of the Taiwan Straits and Yangtze River Delta, promoting economic development of northeastern Fujian Province, enhancing the capacity to deal with unexpected events (take natural disasters for instance) and improving the ability to guarantee the emergency traffic.
III. Total investment: RMB 3.339 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: when social discount rate is 8%, economic net present value (ENPV) will reach RMB 1.246 billion and economic internal rate of return (EIRR) will be 11.74%.
V. Preliminary work: at present, report on water and soil conservation of the Project has been examined and approved by relevant provincial department. Preliminary review of land, environmental assessment, demonstration on sea area use, environmental assessment of the ocean, navigation assessment (50000t) and pre-application of sea area use are being conducted. Other prior matters of engineering feasibility have been finished and preliminary survey report has been completed and submitted for approval.
VI. Project organizer: Shenyang-Haikou Multiple Track Expressway Co., Ltd. of
VII. Contact person: Shao Maochan
Tel: 0593-2768127, 18959308080
Fax: 0593-2879670 E-mail: smc-888@sohu.com
122. Connecting Line between Pingnan and Gutian of West Coast Expressway Network
I. Project description: the expressway is planned to be double-way four-lane expressway with total length of
II. Construction reasons and conditions: the project is one of the important links in the "Three Longitudinals, Eight Horizontals and Thirty-three Joints" expressway layout network of economic zone of the west coast of the Taiwan Straits, connecting line between Beijing-Taipei line and Ningde-Shangrao Line of national expressway network and one of fast tracks for connecting inland provinces (take Jiangxi Province for instance) with Fujian Provinces.
III. Total investment: RMB 3.993 billion. Cooperation mode: BOT.
VI. Analysis of economic benefits: the internal rate of return of the Project is 10.41% while the net present value is RMB 987 million (social discount rate i=8%).
V. Preliminary work: at present, engineering feasibility of the Project has been approved and preliminary design has been examined for approval and location survey and acceptance of construction drawing have been completed. It is planned that design documents of construction drawing will be examined and approved in July.
VI. Project organizer: Shenyang-Haikou Multiple Track Expressway Co., Ltd. of
VII. Contact person: Shao Maochan
Tel: 0593-2768127, 18959308080
Fax: 0593-2879670 E-mail: smc-888@sohu.com
123. Nanping-Shunchang Expressway
I. Project description: the expressway is double-way four-lane expressway with total length of
II. Construction reasons and conditions: the project is one of the most important fast tracks for connecting central and western regions and cities along the coast and has the advantages of higher standard, shorter mileage and more convenient passage when compared with other expressways. It is aimed at adapting to the increasing traffic volume in the future and guaranteeing the clear expressway into
III. Total investment: RMB 4.209 billion. Cooperation mode: BOT.
IV. Project organizer: Yanshun Expressway Co., Ltd. of
V. Contact person: Jin Guoping
Tel: 13860078982 E-mail:npys@163.com
124. Nanping Connecting Line Expressway
I. Project description: the expressway is double-way four-lane expressway with total length of
II. Construction reasons and conditions: the project is one of the most important fast tracks for connecting central and western regions and cities along the coast and has the advantages of higher standard, shorter mileage and more convenient passage when compared with other expressways. It is aimed at adapting to the increasing traffic volume in the future and guaranteeing the clear expressway into
III. Total investment: RMB 4.5 billion. Cooperation mode: BOT.
IV. Project organizer: Yanshun Expressway Co., Ltd. of
V. Contact person: Zheng Jingfu
Tel: 13860010777 E-mail: 13860010777@163.com
125. Zhongxian-Banmian Section in Sanming City of Meizhou Bay-Chongqing Expressway
I. Project description: the project starts from Gaiyang Town (K137+151), junction between Yongtai County and Youxi County, goes into Youxi County of Sanming City through Wuleige Tunnel with construction mileage of
II. Construction reasons and conditions: the project is of great importance for promoting coordinated development among different regions, strengthening ties between west coast of the Taiwan Straits and Changsha, Zhuzhou, Xiangtan and Chengdu and Chongqing, promoting construction of economic zone of west coast of the Taiwan Straits, perfecting external transportation pattern of west coast of the Taiwan Straits, broadening port cluster of Meizhou Bay, improving port competitiveness and realizing benign economic complement between port and the interior areas.
III. Total investment: RMB 2.98 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: it is recommended in the project that the financial internal rate of return (after tax) should be 5.52%, financial net present value RMB 2.16 billion and payback period 18.02 years.
V. Preliminary work: this section and environmental assessment has been examined for approval. Report on water and soil conservation and land pre-audit relevant to engineering feasibility has been approved. Minerals below construction have been assessed. Design has been accepted by the preliminary survey in the field; preliminary design documents have been compiled for reporting.
VI. Project organizer: Meiyu Expressway Co., Ltd. of
VII. Contact person: Chen Haixian
Tel: 13906086366 Fax: 0598-8520302 E-mail: smyxg16@163.com
126. Youxi (Banmian)-Shaxian Section in Sanming City of Xiasha Expressway (Xiamen-Shaxian Expressway)
I. Project description: the expressway starts from
II. Construction reasons and conditions: the project is aimed at perfecting the expressway network of economic zone of west coast of the Taiwan Straits, building the fast track between
III. Total investment: RMB 5.326 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: financial internal rate of return (FIRR) of the Project is 5.65%, higher than 3.47% the benchmark financial discounting rate. Financial net present value (FNPV) is RMB 535 million, dynamic investment-payback period (Pt) is 16.1 years and repayment period of bank loan of the Project (Pd) is 16.48 years.
V. Preliminary work: at present, engineering feasibility of the Project has been approved by the provincial development and reform commission and preliminary design documents have been complied and examined for approval. It is planned to start construction from Q3, 2012.
VI. Project organizer: Xiasha Expressway Co., Ltd. of
VII. Contact person: Liang Daosheng
Tel: 13358509716 Fax: 0598-8520302
E-mail: smyxg16@163.com
127. Daping-Datian Guangping Section in Sanming of Meizhou Bay to Chongqing Expressway
I.Project description: the section starts at K161+797.616 of Daping Interchange, and ends at K202+800 of the Southwest of Taozhou County. The line is planned to be 41.002 km in length.
II. Construction reasons and conditions: the project strengthens the connection of the three economic zones: Economic Zone of western coast of the Taiwan Straits, Chang-Zhu-Tan economic zone, and Cheng-Yu economic zone, improves the transportation pattern to the outside of west coast of the Taiwan Straits Zone, expands the hinterland of harbor groups on Meizhou Bay, enhances the competitiveness of harbors, realizes the benign complementary of economic development between harbors and inland areas, and establishes vital transportation lanes between inland provinces like Chongqing, Hunan and Jiangxi, and Southeastern coastal region.
III. Total investment: RMB 3.96 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: according to the calculation, the financial internal rate of return of the recommended program of the Project is 5.52%, financial net present value is 2.16 billion, and the payback period is 18.02 years.
V. Preliminary work: the feasibility of the project and the supporting soil and water conservation and environmental evaluation have been examined and are currently under approval, the pre-examination of land use has approved, mineral resources below construction have evaluated; the pre-examination of preliminary design has finished, and the data of preliminary survey field acceptance has been submitted for approval.
VI. Project organizer: Meiyu Expressway Co., Ltd. of
VII. Contact person: Chen Haixian
Tel: 13906086366
Fax: 0598-8520302 E-mail: smyxg16@163.com
128. Guangping -Shenkou Section in Sanming of Meizhou Bay to Chongqing Expressway
I. Project description: the section starts at the hillside of the southwest of Taozhou Village, Pingguang Town, Datian County, the station number of which is K202+800, and ends at Panxi Interchange, the station number of which is K249+238.788. The line is planned to be 46.439 km in length.
II. Construction reasons and conditions: the project strengthens the connection of the three economic zones: Economic Zone of western coast of the Taiwan Straits, Chang-Zhu-Tan economic zone and Cheng-Yu economic zone, improves the transportation pattern to the outside of west coast of the Taiwan Straits Zone, expands the hinterland of harbor groups on Meizhou Bay, enhances the competitiveness of harbors, realizes the benign complementary of economic development between harbors and inland areas, and establishes vital transportation lanes between inland provinces like Chongqing, Hunan and Jiangxi, and Southeastern coastal region.
III. Total investment: RMB 3.85 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: according to the calculation, the financial internal rate of return of the recommended program of the Project is 5.52%, financial net present value is 2.16 billion, and the payback period is 18.02 years.
V. Preliminary work: the feasibility of the Project and the supporting soil and water conservation and environmental evaluation have been examined and are currently under approval, the pre-examination of land use has approved, mineral resources below construction have evaluated; the pre-examination of preliminary design has finished, and the data of preliminary survey field acceptance has been submitted for approval.
VI. Project organizer: Meiyu Expressway Co., Ltd. of
VII. Contact person: Chen Haixian
Tel: 13906086366 Fax: 0598-8520302
E-mail: smyxg16@163.com
129. Mingxi County Town-Fengxi Section of Meizhou Bay to Chongqing Expressway
I. Project description: Mingxi County Town-Mingxi Fengxi Section in Sanming of Meizhou Bay to Chongqing Expressway starts at Mingxi Interchange (the station number: K280+574.367) which connects the end of Sanyuan Shenkou-Mingxi County Town section, and ends at the starting point of Mingxi Fengxi-Jianning Lixin section (the station number: K331+200) near Fengxi Huangjiadi. The line is planned to be 50.626km in length.
II. Construction reasons and conditions: the project strengthens the connection of the three economic zones: Economic Zone of western coast of the Taiwan Straits, Chang-Zhu-Tan economic zone, and Cheng-Yu economic zone, improves the transportation pattern to the outside of west coast of the Taiwan Straits Zone, expands the hinterland of harbor groups on Meizhou Bay, enhances the competitiveness of harbors, realizes the benign complementary of economic development between harbors and inland areas, and establishes vital transportation lanes between inland provinces like Chongqing, Hunan and Jiangxi, and Southeastern coastal region.
III. Total investment: RMB 4.8 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: According to the calculation, the financial internal rate of return of the recommended program of the Project is 5.52%, financial net present value is 2.16 billion, and the payback period is 18.02 years.
V. Preliminary work: the feasibility of the Project has been examined and under approval, the assorted water protection and environmental evaluation examined and under approval, the preliminary examination of land approved, mineral resource evaluated; and the preliminary survey field acceptance has been finished.
VI. Project organizer: Meiyu Expressway Co., Ltd. of
VII. Contact person: Chen Haixian
Tel: 13906086366
Fax: 0598-8520302 E-mail: smyxg16@163.com
130. Sanming Fengxi-Jianning (junction of Fujian and Jiangxi) Section of Meizhou Bay to Chongqing Expressway
I. Project description: Mingxi Fengxi-Jianning Lixin Section in Sanming of Meizhou Bay-Chongqing Expressway starts at the end point of Mingxi County Town-Mingxi Fengxi Section near Fengxi Huangjiadi (the station number: K331+200), and ends at the junction of Zhujia Interchange and Jiantai Expressway (Jianning-Taining Expressway, the station number: K376+308.712). The line is planned to be 45.955 km in length.
II. Construction reasons and conditions: the project strengthens the connection of the three economic zones: Economic Zone of western coast of the Taiwan Straits, Chang-Zhu-Tan economic zone, and Cheng-Yu economic zone, improves the transportation pattern to the outside of west coast of the Taiwan Straits Zone, expands the hinterland of harbor groups on Meizhou Bay, enhances the competitiveness of harbors, realizes the benign complementary of economic development between harbors and inland areas, and establishes vital transportation lanes between inland provinces like Chongqing, Hunan and Jiangxi, and Southeastern coastal region.
III. Total investment: RMB 3.2 billion. Cooperation mode: BOT.
IV. Analysis of economic benefits: According to the calculation, the financial internal rate of return of the recommended program of the Project is 5.52%, financial net present value is 2.16 billion, and the payback period is 18.02 years.
V. Preliminary work: the feasibility of the Project and the supporting soil and water conservation as well as environmental evaluation have been reviewed and are currently under approval; the pre-examination of land use has been approved, mineral resources below construction have been evaluated; the preliminary survey field acceptance has been finished.
VI. Project organizer: Meiyu Expressway Co., Ltd. of
VII. Contact person: Chen Haixian
Tel: 13906086366 Fax: 0598-8520302
E-mail: smyxg16@163.com
131. Zhangzhou Coastal Thoroughfare (Zhao'an Section)
I. Project description: a total length of 27.93km is designed as per Class I highway standard with the roadbed width of 24.5m in total and the cement concrete pavement width of 15m.
II. Construction reasons and conditions: the construction of the Project is a necessity for the development of Coastal Highway of Fujian Province, compliant with strategy of "Development based on port" put forward by Zhangzhou Municipal Party Committee and Government for the purpose of improving the traffic network and freight collecting and distributing in port area, developing the port economy and establishing city cluster of Xiamen, Quanzhou and Zhangzhou.
III. Total investment: RMB 620 million. BT mode is planned to be adopted for construction.
IV. Analysis of economic benefits: the internal rate of return of the Project is 10.75%.
V. Preliminary work: the feasibility report has been completed and is currently under review for approval.
VI. Project organizer: Zhaoan Transportation Construction and Development Co., Ltd.
VII. Contact person: Zhong Songmao
Tel: 0596-3326974, 13606998978
Fax: 0596-3331638 E-mail: zzsza0596@163.com
132. Sanming Changshen Expressway Connecting Line
I. Project description: the line is planned to be 74.388km in length; in addition to Sanming County Town section, the actual construction length is 63.982km; it is designed as per Class I highway and urban expressway standard with the running speed to be 60-80km/h; the two-way six-lane expressway is planned to be adopted in the Chafengxia-Shenkou section and Gongchuan-Yong'an north interchange section (51km), while the two-way four-lane in Shenkou-Gongchuan Section (13km).
II. Construction reasons and conditions: the project responses to and complies with the development of west coast of the Taiwan Straits, implements the "harbor building and sea access" strategy, makes use of the advantages of the northwest of Fujian, facilitates the demand of economic advantage transformation; it is the demand of constructing the main transportation axis of Sanming Ecological Industrial and Trade Area, the key development region of Fujian, and the demand of constructing the convenient, fast-accessed lanes of Sanming airport, railway, highway and the main places of Sanming.
III. Total investment: RMB 7.157 billion.
IV. Analysis of economic benefits: according to the calculation of benefits and costs during the evaluation period, the national economic internal rate of return (EIRR)of the Project is 11.26% (8% higher than the social discount rate); the economic net present value is RMB 358,788,000; the economic benefit cost ratio is 1.49; and the investment payback period is 16.1 years.
V. Preliminary work:
VI. Project organizer: Sanming Changshen Expressway Connecting Line Co. Ltd.
VII. Contact person: Guo Shideng
Tel: 0598-8219956, 13859133008
Fax: 0598-8267633 E-mail:1586779758@qq.com
133. Construction Project of Xianyou Laixi-Xiyuan Fengshan Section
I. Project description: a total length of 18.4km is designed as per Class II highway standard (partially as per Class III highway standard) with the roadbed width of 8.5m in total and the cement concrete pavement width of 7m.
II. Construction reasons and conditions: the project is planned to fulfill the demand of connecting Shenyang-Haikou Multiple Track Expressway; the demand of improving the highway trunk line network of
III. Total investment: RMB 190 million. BT is planned to be adopted for the construction.
IV. Analysis of economic benefits: return on investment depends on the interests in buyback period and construction period and the maintenance and appreciation of credit deposit for project resettlement paid by the Bid Inviter to the Bid Winner as investment builder, including: [1] annual interest rate in construction period is 8% (return including construction costs is 50%); [2] buyback period is divided into two years (40%:30%:30%), the return rate is 12% in the first year and 14.4% in the second year; [3] credit deposit may preserve and increase its value (used for project resettlement and other preliminary work) with a return rate of 14.4%.
V. Preliminary work: construction drawing design has been completed.
VI. Project organizer: Transportation Bureau of Xianyou County
VII. Contact person: Wang Guobin
Tel: 0594-8592449, 0594-8391993, 15105941307
Fax: 0594-8397332 E-mail: 420857474@qq.com
134. Reconstruction Project of Suban Township of Xinluo District - Tieshan - Dongxiao - Hongfang - Gaopo Town of Yongding County Section of Provincial Road 203
I. Project description: the line of Phase I Project and Phase II Project are 40 km and 19.1km respectively, totally 59.1km. It is designed according to the standard of first-class highway & class I urban trunk, with bi-directional 6 lanes as the main traffic lane; the running speed of the main line is designed to be 60km/h and that of the side road is designed to be 30km/h. The subgrade width of common segment of Phase I Project is 32m while that of Phase II Project is 36m. The subgrade width of the segment passing through town of both Phase I and Phase II Project is 50m. In addition, bitulith road surface is applied.
II. Construction reasons and conditions: in accordance with the development strategy of Longyan-"One main urban area, three new towns and one satellite town", the implementation of the Project will be good for the connection of the two new towns (Yanbai New Town and Gaokan New Town), greatly improve the transportation capacity of Provincial Road 203, accelerate the development of central Longyan, adapt the trend of diversification development, improve the central function and enhance diffusing function.
III. Total investment: RMB 4.17 billion, including RMB 2.78 billion of Phase I and RMB 1.39 billion of Phase II. BT mode is planned to be adopted for the construction.
IV. Analysis of economic benefits: as for Phase I Project, it is calculated that when social discount rate is 8%, economic net present value (ENPV) is RMB 1,117.38 million and economic internal rate of return (EIRR) will be 11.53% (8% more than social discount rate), the economic benefit cost ratio (EBCR) of the Project will be 1.52 (more than 1).
V. Preliminary work: the feasibility study report of Phase I Project had been pre-examined by the Municipal Government on Oct. 21, 2011, and now has been submitted to the Provincial Government for further examination. As for Phase II Project (K0+000-K6+000) stretching from southern section of Dongxiao Town Longyan Road to Hongfang Town section, the examination of working drawings had been carried out on Mar. 20, 2012, and now the working drawings is under revision.
VI. Project organizer and contact person
Project organizer of Phase I Project: Transportation Bureau of Xin Luo District,
Contact person: Luo
Project organizer of Phase II Project: Longyan Economic Development Zone
Contact person: Lai Qingtao Tel: 13959029828
135. Reconstruction Project of Gutian Gaotouling- Juxia Section of Provincial Road 202
I. Project description: the Project, 11.126 km in length, is designed according to the standard of Class II urban trunk, with a subgrade width of 24m or 36m, and the running speed is designed to be 60km/h.
II. Construction reasons and conditions: the project is one section of Provincial Road 202 within Gutian area, and also an important part of the road access to
III. Total investment: RMB 668.4072 million. BT mode is planned to be adopted for the construction.
IV. Analysis of economic benefits: where social discount rate is 8%, the economic benefit cost ratio (EBCR) of the Project is 1.5587, economic net present value (ENPV) is RMB 263.9078 million, economic internal rate of return (EIRR) will be 11.95%, and the EN of it is 16.79 years.
V. Preliminary work: the feasibility study report has been completed and is under examination and approval.
VI. Project organizer:
VII. Contact person: Lin Jisong
Tel: 0593-3833151, 15859301107
Fax: 0593-3833150 E-mail:gt3833153@126.com
136. Construction Project of Pingnan Countytown (Jialong Roundabout) -Western Pingxi Section of Provincial Road 303
I. Project description: the total length of the Project is 51.28km and the running speed is designed to be 40km/h. The section from the starting point to Cixi which is 3.25km in length, is designed according to the standard of Class II urban trunk, with a subgrade width of 36m and bitulith concrete surface; the section from Ciuxi to the end which is 48.03km in length, is designed according to the standard of Class II urban trunk, with a subgrade width of 8.5m and full-width cement concrete surface.
II. Construction reasons and conditions: the project is the third horizontal road of the "Eight Longitudinal and Night Horizontal " provincial trunk highway network, and the main truck highway leading to Northern Fujian, Wuyi Mountain tourism area and Northen Jiangxi Province; the Project will help Pingnan county better receive the economic radiation from surrounding cities, promote the communication and cooperation of economics, culture, tourism and trade between different areas, and also meet the demand of developing industrial and agricultural investment.
III. Total investment: RMB 760.71 million. BT mode is planned to be adopted for the construction.
IV. Analysis of economic benefits: where social discount rate is 8%, the national economic evaluation result of the Project total investment is as follow: the economic benefit cost ratio (EBCR) of the Project is
1.5366, economic net present value (ENPV) is RMB 274.8696 million, economic internal rate of return (EIRR) will be 12.39%, and the investment payback period is 15.17 years.
V. Preliminary work: the feasibility report has been completed and is currently under review for approval.
VI. Project organizer: Transportation Bureau of Pingnan County
VII. Contact person: Lu Changbin
Tel: 0593-3326271, 13509566138 Fax: 0593-3309881 E-mail: lcb158@126.com
扫一扫在手机上查看当前页面